outsourcing, crowdsourcing, remote worker, teleworker, freelance,web, development, software, networking, information systems, electronics, creative arts, writing, translations, design arts, multimedia, administrative support,business services, customer service, sales and marketing, advertising, legal, paralegal

 
How work gets done. Guaranteed.

Mediation / Arbitration (Dispute Resolution) for

Winsock monitor command line tool: (Messages | Project)
Arbitration id: 115904 | Bid Id: 36207605

THIS ARBITRATION IS PUBLICLY VIEWABLE
Employer :

 scottie05 Profile

Employer Business address :

 From Boca Raton, Florida, United States


Worker :

 MOTASH Profile

Worker Business address :

 From Beni Ebeed, Dakahlyia, Egypt


Arbitration Summary : 

   Allegation Summary:

Motash initiated an arbitration to resolve a contract dispute, stating that there was a disagreement over which MSN version for the project needed to be used.  The arbitrator noticed that the employer had not set a deadline after the old deadline has passed (a situation called “implicit deadline extension”). So a new deadline needed to be set to allow work to continue. Before that could happen, both parties needed to agree on the contract.  Several project issues were brought up by both parties that were resolved.  Then a new deadline was set and work continued.  When work continued, the employer discovered additional bugs which they reported, but closed their account before the project deadline expired and forfeited the arbitration.  Shortly thereafter, Motash was forfeited because he had made inappropriate additional statements despite being warned previously.

   Arbitration Summary:

This project was brought into arbitration by Motash (the worker) to resolve a contract dispute. Motash stated that there was a disagreement over which MSN version needed to be used. Scottie8 (the employer) stated that “tested the product on four versions of MSN in three OSes and it crashed on all of them all of the time.” Motash disputed this and brought up additional points as well and the project went for technical analysis.

Since this project was not 100% complete, work would continue on the project. Both the employer and worker were offered self-mediation, but they could not come to an agreement on the funds.

In technical arbitration, the arbitrator stated that the latest version of MSN available at that point in time would be used and the testing environment would be 32 bit. Motash stated:
the employer gave a feedback that a fault in my program based on a test on platforms(64bit) that were not part of the contract, and when i noticed that and faced him, he said that same faults exists on agreed platforms(32bit),but these faults he claimed didn't exist in the data he provided as a feedback
** i see if my allegation in this point is confirmed by the technical arbitrator, then the employer is preventing work from being completed


The arbitrator ruled that the employer did not prevent work from being completed by testing on a 64 bit version of Windows. 

Motash stated:
Which version of MSN?
-the latest version,that's clear to me

2. Which environment do the deliverables have to work on?
clear to me,32 bit platforms as per Posting # 36,355,035, but to be more specific as this posting is an extension to Posting # 36,355,031, so specifically i believe its :
ONLY XP SP3, Vista SP1, Windows 7 on 32bit platform

3. Are extra features added by the worker considered part of the contract?
NOT CLEAR, since we are technically speaking,we should not consider a general answer for general request, as it had been subject to clarification and not been answered in its detailed form on Arbitration Response Ids: 1,669,116 , 1,669,871


After this, Motash brought up several issues regarding the employer’s previous responses and re-raised the issue that it prevented him from completing the work because he tested in a 64 bit environment. He was given a warning reminding him to remain professional or he would forfeit the arbitration in Arbitration Response Id: 1,674,883.

The arbitrator looked at the employer’s responses and reconfirmed that his actions did not prevent the work from being completed, since he had also tested in a 32 bit environment and posted the results. Since the project was an implicit deadline (The deadline had expired, work continued, and no new deadline was set), work was to continue.

On Monday Sep 26, 2011 2:56:06 PM, Motash did receive a warning for the following statements:
My Reply:that's not true, any agreed details by both parties in their conversation is part of the specs, and I'M SURPRISED THAT YOU DIDN'T REPLY HIM
and
as a judging party,i expect you not to follow nor show what you THINK on behalf of any party, until BOTH parties show their allegations(you did so on arbit. resp. ID: 1,672,194 before the employer gave his reply)

Diane did bring up issues regarding the implicit deadline because Motash had marked the project complete. The implicit deadline rules were explained – if the project goes past the deadline and work continues without a deadline being set, the project is in an implicit deadline situation and work continues. Motash was also warned not to respond to the other person’s post – as this warning was given previously in Arbitration Response Id: 1,664,366.

Motash had an issue regarding the MSN version as they had trouble getting MSN to work on their computer.

Both parties could not agree on a deadline, Diane requested 24 hours and Motash requested “5 days from a fix is provided”. As both parties could not agree on a deadline, the arbitrator imposed a deadline of 3 days. Scotie8 (the employer) did not agree to the length of the deadline, but did set the deadline onsite. The issue regarding not setting a new deadline when the old deadline expired was again explained to Scotie8.

Work began and both parties responded back and forth to each other. In Arbitration Response Id: 1,683,366, Motash was again warned for giving opinions. After getting the warning Motash posted a list of statements to determine if they were opinions or not.

Scotie8 posted a list of defects. However, before the end of the deadline to complete the work, they deliberately forfeited the arbitration and closed their account without waiting to see if Motash was going to fix the issues before the end of the deadline.

Motash was forfeited shortly thereafter when it was determined that he should not have been given a second warning because he had been warned previously. The arbitrator and Motash had a discussion regarding opinions and what constituted opinions. Motash was given an option to go for a review, but declined.



The arbitration process exists to protect parties who fulfill the contract, from those that don't. To ensure that vWorker.com is a safe and fair place to do business, all mediations / arbitrations are settled in accordance with the rules of arbitration as detailed and pre-agreed to by both parties in the employer and worker legal agreements.

IMPORTANT: For legal documentation purposes, you must respond to queries from the arbitrator via this web  page, where it can be documented and stored.  Please do not submit responses by other means (such as email, IM, fax, phone, etc.), as these methods are considered "undocumented" and cannot be taken into account in the arbitration process.


View arbitration documentation (history)
(Showing all postings, in the order they were posted)
Show only the last postings

Date: Tuesday Sep 6, 2011 10:16:51 AM (Arbitration Response Id: 1,663,420)
From: Ian Ippolito (vWorker) (Arbitrator)
To: scottie05 (employer),MOTASH  (worker)
 
Note: 3 long word(s)/URL(s) in this posting > 65 characters was/were broken up with spaces to prevent it/them from stretching the screen and making it difficult to read.

The project (Winsock monitor command line tool) has been entered into mediation/arbitration, as requested by either yourself or another party.

To ensure that vWorker.com remains a safe and fair place to do business, all mediations / arbitrations are settled in accordance with the rules of mediation/arbitration as detailed and pre-agreed to by both parties in the employer and worker legal agreements:

Employer Agreement: http://www.vworker.com/RentACoder/DotNet/misc/Legal/SoftwareBuye rLegal.aspx#arbitration
Worker Agreement: http://www.vworker.com/RentACoder/DotNet/misc/Legal/SoftwareSell erLegal.aspx#arbitration

The mediator/arbitrator will be sending follow-up notices to you detailing what (if anything) you need to do. It is VITAL (for legal documentation purposes) that you always respond via the website (a link is provided under each email notification, as well as in your 'to do' list), where it can be documented and stored. Please do not submit responses by other means (such as email, IM, phone, fax, etc.), as these methods are considered 'undocumented' and cannot be taken into account in the arbitration process. To prevent your arbitrator from being unfairly influenced by one party, neither of you may initiate phone calls to the arbitrator to discuss the arbitration.

If you are asked a question or asked to complete a task, please be prompt in your replies. You have a maximum of 3 business days to respond (or 5 business days if you are an employer being asked to either accept a work 100% or produce a flaw list). If you can respond sooner, the process will move along quicker for everyone. If you do not respond in time, you will forfeit the arbitration (as you've legally agreed in your contract). Please do not let this happen to you. Note: if you have a vacation (or other legitimate reason for an absence), an exception can be made to this rule. But to guarantee it, you must inform your arbitrator in advance, at least 2 business days for each week of absence (and a minimum of 3 business days). If you have any upcoming planned absences in the near future, we strongly suggest that you announce them now, to avoid a potential timing problem later. For more information, see 'Excused absences' in your employer or worker agreement.

MOTASH, IF you have not uploaded the latest deliverables to the site and the deadline for this project has NOT yet arrived, then please immediately upload them to the status report section. If you wait more than 1 working day (or until after the deadline, whichever comes first) and this arbitration requires testing, we ONLY test deliverables that were previously uploaded on site. And if you have no deliverables on site, you will forfeit the arbitration. Please remember that it is important on every project to ALWAYS upload your deliverables periodically to the site, so that you are protected in case of a dispute.

All monetary amounts displayed are the total amounts escrowed by the employer. If you are the worker, please remember that this is *different* than the amount you bid (because it includes the vWorker.com fee). So when discussing amounts, remember to use the employer escrow amount, and not the amount you bid. For full information on the difference between the employer escrow amount and the worker bid, click here: http://www.vworker.com/RentACoder/DotNet/SoftwareBuyers/Software BuyerFAQ.aspx#cost

If you have any questions not answered by the above links, just post your question to the mediation/arbitration and your mediator/arbitrator can assist you.


 

 
Date: Tuesday Sep 6, 2011 10:16:52 AM (Arbitration Response Id: 1,663,421)
From: MOTASH (worker)
To: Ian Ippolito (vWorker)  (arbitrator)
 
 This message was sent privately

Self-initiated mediation / arbitration.
Type: Want vWorker.com to resolve contract term(s) dispute
 

 
Date: Tuesday Sep 6, 2011 10:16:52 AM (Arbitration Response Id: 1,663,422)
From: Ian Ippolito (vWorker) (Arbitrator)
To: MOTASH  (worker)
 
 This message was sent privately

Note: 2 long word(s)/URL(s) in this posting > 65 characters was/were broken up with spaces to prevent it/them from stretching the screen and making it difficult to read.

     I'm putting this bid into arbitration right now to get this issue resolved.

     The rules of arbitration were created to ensure a fair and safe environment for employers and workers and is in your contract at: http://www.vWorker.com/RentACoder/DotNet/misc/Legal/SoftwareBuye rLegal.aspx#arbitration

     I am contacting the other party right now...

Sincerely,
Ian Ippolito (vWorker)
vWorker.com Arbitrator
============================================
www.vWork er.com
Need an expert? Hire the best and brightest global talent
with the safety of a money back guarantee!

P: (813) 908-9029
F: (813) 960-1495
E: IanIppolito@Planet-source-code.com
Exhedra Solutions, Inc.
============================================
 

 
Date: Tuesday Sep 6, 2011 10:16:52 AM (Arbitration Response Id: 1,663,423)
From: Ian Ippolito (vWorker) (Arbitrator)
To: scottie05 (employer)
CC: MOTASH  (worker)
 
Note: 2 long word(s)/URL(s) in this posting > 65 characters was/were broken up with spaces to prevent it/them from stretching the screen and making it difficult to read.

The worker has informed us that the two of you disagree over one or more contract issues...specifically:

"Q1 Answer : the employer asked to inject a logger DLL into the process of three executables (MSN , IE v8 , Chrome v12), so i got it working for the three programs, and after i sent him the code and log proofs,he asked for a solution for an older version of MSN that's not available,in a good faith i tried to investigate the issue, but MSN is an online setup, and that version is not available,i asked if he has an installable source for it,but never had a reply,and i commit to the original open post, that i've already fulfilled

Q2 Answer : a proof of MSN logging success exists in the attachment sent on "Monday Aug 22, 2011 10:17:07 PM EDT" path in compressed file : \IMCATRUN\DEBUG\test.log
"

If the above is true and if the two of you truly cannot come to an agreement, then both of you have pre-agreed (in your contracts with us) that vWorker.com would then become the final and legally binding interpreter of this contract.

We will begin that process now by first getting your position on this disagreement. After I understand both of your positions, I will then review both of your allegations versus the contract that the two of you created. Once this is completed, a final ruling will be made. If the subject matter demands it, this arbitration will be transferred to a technical arbitrator.

As a reminder the contract is composed of:
  1. All information on the project page (title, description, compatibility, etc.)
  2. All onsite amendments that are agreed to by both parties.
These things are NOT a part of the contract:
  1. Things that a party "meant" to put in the contract but neglected to.
  2. Any amendments allegedly communicated offsite (These are too easy to fake, where even a professional cannot determine if it's real or a forgery and thus not admissible.)
  3. Anything that was not agreed to be done by both parties

-----------------------------------------------------

Please let me know your position in this disagreement and then we can proceed. While you have up to 3 business days to respond, this arbitration will go much faster for everyone if both parties can respond more promptly. Thanks.

Sincerely,
Ian Ippolito (vWorker)
vWorker.com Arbitrator
============================================
www.vWork er.com
Need an expert? Hire the best and brightest global talent
with the safety of a money back guarantee!

P: (813) 908-9029
F: (813) 960-1495
E: IanIppolito@Planet-source-code.com
Exhedra Solutions, Inc.
============================================
 

 
Date: Tuesday Sep 6, 2011 10:16:53 AM (Arbitration Response Id: 1,663,424)
From: Ian Ippolito (vWorker) (Arbitrator)
To: scottie05 (employer),MOTASH  (worker)
 
Responsibility for this mediation / arbitration is being assigned to arbitrator Michele Nisi (vWorker).
 

 
Date: Tuesday Sep 6, 2011 10:16:53 AM (Arbitration Response Id: 1,663,425)
From: Ian Ippolito (vWorker) (Arbitrator)
To: Michele Nisi (vWorker)  (arbitrator)
 
 This message was sent privately

This arbitration was auto-assigned to you.
 

 
Date: Tuesday Sep 6, 2011 11:57:58 AM (Arbitration Response Id: 1,663,465)
From: scottie05 (employer)
To: Michele Nisi (vWorker)  (arbitrator)
CC: MOTASH  (worker)
 
The above is not correct. I did not ask for an additional version of MSN messenger to be included.

I tested the product on four versions of MSN in three OSes and it crashed on all of them all of the time.

I dispute the worker's proof that his uploaded log demonstrates that it works -- it only demonstrates that it works in his development environment. I have not been able to make it work on any PC, whether a real-world PC or a virtual machine in our test lab.

I uploaded an example of one of the crashes, which happened to be the older one to which the worker is referring, but I also offered to set up a remote debugging environment for the others, which the worker declined.

The worker is asking me to accept the work as complete when it is too unstable to use. I can accept missing features or final details to be cleaned up later , but not a program that crashes all of the time.

The worker stated that they 'give up', rather than investigate more and resolve the issue, which puts me in a difficult situation. I have a product that does not work and is no use to me whatsoever.

I paid for working deliverables, and I would settle for working deliverables.

Sincerely
DaveP

 

 
Date: Tuesday Sep 6, 2011 2:15:43 PM (Arbitration Response Id: 1,663,673)
From: MOTASH (worker)
To: Michele Nisi (vWorker)  (arbitrator)
CC: scottie05 (employer)
 
FIRST : The employer claims he tested the code on four versions of MSN and over 3 OS's and disputes the log i sent,i hope he specifies those versions along with the OS's, plus give proof in our contract of a specific version of MSN, like specified in IEv8 , Chrome v12

SECOND : The employer uses the right for NORMAL conditions,and considers my environment as a special case, so
a-i claim the same right,that the contract terms are subject to normal conditions(unless something else is clearly stated), for Ex: if i were asked to put a key into windows registry,and something wrong with the employer registry,or another application is deleting the key i create,.... then it's beyond normal conditions and out of my responsibility
b-i kindly ask for a neutral environment, to have the addressed code be tested on,putting in mind the same circumstances in the flow of progress/feedback(the log was created on MSN v15 on win7)
**Note : a compliance issue with XP was detected later, and covered but the code is not sent yet,i would happily supply the Arbitrator with exe/code to facilitate any verification process,but in private, as i don't want to supply the employer any extra exe/code until the end of the arbitration process)

THIRD : When the employer offered remote debugging option, i didn't decline for no reason, i gave my reasons, not discussing the reasons by the employer makes the declination mutual for the common benefit as i claimed

FORTH :The employer claims a crash in my code and i "given up" : that's the heart of conflict that brought us into arbitration, so here some points to explain
- although the MSN version was not specified,but repeatedly by the employer and me we stated that the requirements are THREE programs(msn,ie v8,chrome v12), so i'm not responsible for every version of MSN, since microsoft created it, and by the right of normal conditions, i got the currently and only available version of MSN to work upon
- i never accepted/agreed to commit to a specific version but to the one i sent the log , all the time i was trying to simulate a CLAIMED crash that i though is a bug inside my code
-i did all my best to verify if the claimed crash inside my code(even the employer clearly stated in his post on Tuesday Aug 23, 2011 11:55:56 AM that the crash inside nt.dll)i added exception handling (SEH , VEH )to catch if any bug happens inside my code, neither me nor the employer could be able to catch a LOG of a crash inside my code, except for one time he claimed he got a SEH Log(which proves the functionality of my exception handling),but i discovered that it was because of the employer tested the code on 64bit OS not on 32bit as agreed,and i would politely say it was a mistake/misleading from him,as after he stated that it happened on both 64/32bit OS's, the logs for 32bit did have no SEH's, which made me doubt his good intentions and judgement, and directly led me to stop further seeking any bugs regarding his claimed crash, and for the sake of courtesy i said i "give up" and accepted a completion ratio
** Mr/Mrs Michele Nisi : that point i called MISLEADING FEEDBACK from the employer is the key point of attitude change between me and the employer, if you follow the conversation between us,so i kindly ask you to investigate/give your judgment for this point in the first place



 

 
Date: Tuesday Sep 6, 2011 5:36:39 PM (Arbitration Response Id: 1,663,968)
From: scottie05 (employer)
To: MOTASH  (worker),Michele Nisi (vWorker)  (arbitrator)
 
Attached File
0.20 MB

To give the worker the benefit of the doubt, in response to the above message I set up a new test machine with a clean version of Windows 7 and Windows Live version 15.4.

I ran the last full version that the worker uploaded (not the "special" upload). It did not crash, but neither did it log any data except the start and end of the process, and nothing else in between. See attached screenshot.

All development environments are special case.

The developer is asserting that, because it works in his development environment, that is good enough.

It is reasonable to expect that the product works outside the development environment.

The developer has marked the project finished, stated he has given up, and I have something that does not work satisfactorily.

I don't have any further points to make.

 

 
Date: Tuesday Sep 6, 2011 6:57:28 PM (Arbitration Response Id: 1,663,997)
From: MOTASH (worker)
To: Michele Nisi (vWorker)  (arbitrator)
CC: scottie05 (employer)
 
i'm a systematic person, taking the employer response and reply to each part of it in specific points,with specific words,dates,.. as much as possible

of course i have much to answer what the employer wrote in his last reply, but that would be much like an endless chat

-i sent a specific answer for the 2 questions offered by vworker
- the employer replied in 'what i see as' a bulky unspecified points
-i gathered every point/topic mentioned in his reply, and gave a specific response/clarification/request
-right now the employer thrown away all points mentioned,jumps all over them, and states unjustified result

so i expect you Mr/Mrs Michele Nisi : to understand that i really don't know how to answer :
-should i throw all replies away, and say what i want to say, and jump to unjustified conclusions
-or should i keep counting unanswered points first,second,third,.. for ever

kindly put a point of order, and advice, for this arbitration to reach a fruitful result
 

 
Date: Wednesday Sep 7, 2011 11:25:07 AM (Arbitration Response Id: 1,664,366)
From: Michele Nisi (vWorker) (Arbitrator)
To: scottie05 (employer),MOTASH  (worker)
 
scottie05, MOTASH,

Thank you for the responses. After reviewing your responses it seems that the dispute comes down to a simple issue, whether or not the work is complete.

I'm going to ask that you don't respond to what the other person posts anymore unless I ask you to do that. That will help us keep the arbitration moving quickly.

MOTASH,

Are you alleging that the work is 100% complete? If so, can you give me the posting ID where you uploaded the deliverables to vWorker?

Michele Nisi (vWorker)

P.S. Automated warning about upcoming deadline(s). Worker must respond before Monday Sep 12, 2011 11:25:07 AM EDT. If you can respond sooner, please do so, as it will speed up the arbitration process for both parties. Thanks.
 

 
Date: Wednesday Sep 7, 2011 12:06:09 PM (Arbitration Response Id: 1,664,419)
From: MOTASH (worker)
To: Michele Nisi (vWorker)  (arbitrator)
CC: scottie05 (employer)
 
To answer the employer points, yes i do allege a work complete(by the given original work specs , and message conversations between us), by the final sent status report on Tuesday, Sep 6, 2011 9:13:17 PM EDT

but my point ( and what i arbitrate for):-

1- the employer did give incorrect/misleading feedback to me, and not answering it neither in project private messages nor in this arbitration makes me assume bad intentions, which may be considered as an act of lie, that makes me:
a- ask not to use the default behavior that the test venue is hosted by the employer, and as i claim that work complete i wouldn't host it,i better ask for a neutral test environment
b-ask if that unethical act is proven, that the employer gets punished,by at least mentioning it as a result of arbitration on his profile , and giving me exclusive IP over any code made beyond the original stated specs

2- by claiming a bug/crash in my code and disputing the log evidence i sent, supported by the unethical act mentioned before, i ask the code sent on "Monday Aug 22, 2011 10:17:07 PM EDT" to be tested for crash in the same circumstances, if worked, may the employer be extra charged with the an appropriate amount(based on the hour rate agreed by the employer or another value the arbitrator decides)

MOTASH
 

 
Date: Thursday Sep 8, 2011 11:46:28 AM (Arbitration Response Id: 1,665,087)
From: Michele Nisi (vWorker) (Arbitrator)
To: scottie05 (employer),MOTASH  (worker)
 
MOTASH,

Thank you for the response. I wanted to respond to what you've alleged:

>>1- the employer did give incorrect/misleading feedback to me, and not answering it neither in project private messages nor in this arbitration makes me assume bad intentions, which may be considered as an act of lie, that makes me:

I understand what you are saying. It is always best not to make assumptions because your assumptions could be wrong. Remember that you are protected if you follow your agreement and meet the contract, so you won't need to worry about making assumptions to protect yourself.

>>a- ask not to use the default behavior that the test venue is hosted by the employer, and as i claim that work complete i wouldn't host it,i better ask for a neutral test environment

I won't be handling testing so this is something that the technical arbitrator will review with you after addressing the testing rules.

>>b-ask if that unethical act is proven, that the employer gets punished,by at least mentioning it as a result of arbitration on his profile , and giving me exclusive IP over any code made beyond the original stated specs

Anytime a party is found at fault in arbitration we document it. So if either party did something wrong, it is possible they will lose arbitration or receive a poor rating.

>>2- by claiming a bug/crash in my code and disputing the log evidence i sent, supported by the unethical act mentioned before, i ask the code sent on "Monday Aug 22, 2011 10:17:07 PM EDT" to be tested for crash in the same circumstances, if worked, may the employer be extra charged with the an appropriate amount(based on the hour rate agreed by the employer or another value the arbitrator decides)

Regardless of what may be proved in testing, the employer won't be charged any additional amount for anything. The contract is for a specific amount of funds, which is already in escrow. We don't handle any type of payments for time lost. This goes for both employers and workers.


MOTASH,

I understand you are alleging that the work is 100% completed. We can test the deliverables to verify this, and if we do, then you will receive payment of the remaining funds from escrow.

However, before doing that, I want you to make sure that you are absolutely certain that the work is indeed completed 100%, and that there are no non-cosmetic flaws. (See the rules of arbitration for the definition.) That is because of this fact: if we find any non-cosmetic flaws during testing, you will lose the arbitration and you won't get paid.

So if there are any non-cosmetic flaws in your deliverables, then you should not be claiming that the work is 100% completed. If you go this route, then the employer must choose to either work with you to the deadline, claim that you made insufficient progress to this point, or forfeit (in which case you'd be paid the percentage we deem as complete).

So after all of this has been explained to you, please let me know if you still allege the work is 100% completed, or if you allege that only a percentage is complete (and then let me know what percent).

Thanks for your response.


Michele Nisi (vWorker)

P.S. Automated warning about upcoming deadline(s). Worker must respond before Tuesday Sep 13, 2011 11:46:28 AM EDT. If you can respond sooner, please do so, as it will speed up the arbitration process for both parties. Thanks.
 

 
Date: Thursday Sep 8, 2011 12:42:36 PM (Arbitration Response Id: 1,665,154)
From: scottie05 (employer)
To: Michele Nisi (vWorker)  (arbitrator)
 
 This message was sent privately

vWorker.com said:You are posting a private message. It is legitimately private?
scottie05 said:I understand that posting privately is generally not allowed because the other party has a right to know all allegations and claims that I make about them, as well as the decisions I've made in arbitration.
scottie05 said:I understand and agree that if ANY of the below GUARANTEEs are incorrect, then I will immediately forfeit this arbitration and possibly my account as well (at Exhedra's discretion) .
scottie05 said:I GUARANTEE that this posting falls completely under one (or more) of the following rare situations:
  • Proprietary/confidential information that the other party does not know AND cannot be revealed to them without causing harm to me.
  • A legitimate question about a different arbitration or project that has no bearing or relation to the current arbitration, whatsoever.
  • A genuine question as to whether a message is appropriate or not. In this case, I have not posted the message itself, but instead summarized the type of information I am considering sending, so the arbitrator can tell me whether it is appropriate or not).
scottie05 said:I GUARANTEE that this posting does not contain any allegations or claims about the other party, nor describe anything that they have done (or allegedly done).
scottie05 said:I GUARANTEE that this posting does not contain any complaints, insults, threats nor opinions about any of the following: the other party, the arbitrator, vWorker.com and/or the arbitration process.

Reason for posting privately:Contains confidential information.

Relates to arbitration process rather than the specific case in question.

Hi Michele,How long does this process take?I have a $56k Deliverable for which this is a prerequisite, and already late, so I need to re-post or traditionally-hire as quickly as possible.Is there any restriction in RAC T+Cs that prevents me from reposting immediately as an urgent project?Sincerely,Dave P
 

 
Date: Thursday Sep 8, 2011 1:31:25 PM (Arbitration Response Id: 1,665,180)
From: MOTASH (worker)
To: Michele Nisi (vWorker)  (arbitrator)
CC: scottie05 (employer)
 
1- regarding my allegation of unethical act of lie from the employer: as we are two parties in an arbitration i can not give a judgement, but i've been asking for your kind investigation/judgement in this issue since my post on Tuesday Sep 6, 2011 2:15:43 PM

2- i started this arbitration on a disagreement between me and the employer about contract issues, that needs to be settled first, then the code i pointed to may be tested against the arbitration results
 

 
Date: Thursday Sep 8, 2011 6:11:40 PM (Arbitration Response Id: 1,665,336)
From: MOTASH (worker)
To: Michele Nisi (vWorker)  (arbitrator)
CC: scottie05 (employer)
 
well, i had the chance to check my application on MSN,IE on another environment,even though MSN v15.4 did have crash troubles and IE was v9, but i found my application behavior is different compared to my environment, there may be something special with my MSN,or other it doesn't matter, but the employer may have some point in his allegation

so, i don't see a point of arguing/proving that the employer did some mistake, nor ethically can i claim that project was complete by attachment on Monday Aug 22, 2011 10:17:07 PM EDT ( as the employer stated that project is accepted only for crash on older version, which can be considered as in section 3A3\3\C "setup program bug")

so,i hereby declare that i forfeit this arbitration, and commit to the consequences as per my work agreement
 

 
Date: Friday Sep 9, 2011 9:19:19 AM (Arbitration Response Id: 1,665,541)
From: Michele Nisi (vWorker) (Arbitrator)
To: scottie05 (employer)
 
 This message was sent privately

Dave,

You can repost this whenever you like. There aren't any restrictions on that. Just keep in mind that the funds are still in escrow on this project and those are not available for reuse. I cannot guarantee what will happen with those funds or the project. So if you repost and choose another worker you will have 2 contracts--the new one with the newly selected worker and this one.

Michele Nisi (vWorker)
 

 
Date: Friday Sep 9, 2011 9:23:32 AM (Arbitration Response Id: 1,665,546)
From: Michele Nisi (vWorker) (Arbitrator)
To: scottie05 (employer),MOTASH  (worker)
 
MOTASH,

Thank you for the response.

>>1- regarding my allegation of unethical act of lie from the employer: as we are two parties in an arbitration i can not give a judgement, but i've been asking for your kind investigation/judgement in this issue since my post on Tuesday Sep 6, 2011 2:15:43 PM

When you are in arbitration we will review the situation and the contract and determine if either party broke it. We can do that but sometimes we need to ask questions and find out other information in order to determine what the parties were responsible for, what should have happened, etc.

>>2- i started this arbitration on a disagreement between me and the employer about contract issues, that needs to be settled first, then the code i pointed to may be tested against the arbitration results

If you are unsure about the contract issues then we can get a technical arbitrator to review that. However Im going to explain how we review the contract because that may be enough for you to determine whether or not you met it. If you still don't know, then just tell me that. But if you do know, then you can tell me.

The arbitration process is used to make sure that the contract (which the two of you created) is honored. If either party (or both) breaks the contract, my job as arbitrator is to enforce the appropriate penalty.

The contract is made up of the following:

  1. All information on the project page (title, description, compatibility, etc.).
  2. All onsite amendments that are agreed to by both parties.
These items are NOT a part of the contract:
  1. Things that a party "meant" to put in the contract but neglected to.
  2. Any amendments allegedly communicated offsite. (These are too easy to fake, where even a professional cannot determine if it's real or a forgery, and thus the communication is not admissible.)
  3. Anything that was not agreed to be done by both parties.
>>well, i had the chance to check my application on MSN,IE on another environment,even though MSN v15.4 did have crash troubles and IE was v9, but i found my application behavior is different compared to my environment, there may be something special with my MSN,or other it doesn't matter, but the employer may have some point in his allegation
so, i don't see a point of arguing/proving that the employer did some mistake, nor ethically can i claim that project was complete by attachment on Monday Aug 22, 2011 10:17:07 PM EDT ( as the employer stated that project is accepted only for crash on older version, which can be considered as in section 3A3\3\C "setup program bug")
so,i hereby declare that i forfeit this arbitration, and commit to the consequences as per my work agreement

Thank you for the feedback. Just because there may be an issue with the work doesn't mean you automatically lose the arbitration. If you don't want to participate in the arbitration anymore then I can let you pull out of it and forfeit arbitration. However you do have the option to continue arbitration and let us review the situation further.

Do you want to continue with arbitration or would you rather stop it and break your contract? If you break your contract you won't receive any funds and will get a 3 rating.

Michele Nisi (vWorker)

P.S. Automated warning about upcoming deadline(s). Worker must respond before Wednesday Sep 14, 2011 9:23:32 AM EDT. If you can respond sooner, please do so, as it will speed up the arbitration process for both parties. Thanks.
 

 
Date: Friday Sep 9, 2011 9:24:13 AM (Arbitration Response Id: 1,665,548)
From: Michele Nisi (vWorker) (Arbitrator)
To: scottie05 (employer),MOTASH  (worker)
 
Note: 1 long word(s)/URL(s) in this posting > 65 characters was/were broken up with spaces to prevent it/them from stretching the screen and making it difficult to read.

scottie05, MOTASH,

The Quick Cancellation Option (Self Mediation)
----------------------------------------------
I need to let both of you know of a 2nd option that you both have available....that would SKIP the formal arbitration process I've described above...and can dramatically speed up the arbitration process for you. vWorker.com (on a trial basis) now offers an opportunity for both parties to mutually agree to a 'Quick Cancellation' without an arbitrator. This process is modeled on the 'no-fault' divorce legal concept in the United States, and instead of focusing on fault it focuses on agreement. This gives you a chance to settle your differences amicably and quicker than the fault finding done in formal arbitration.

If your relationship with the other party is good enough that you can at least attempt to negotiate with them on the issue below, then Quick Cancellation is an option for you. This can results in a conclusion to this arbitration in just a few minutes or hours, rather than days (as can sometimes happen if you both strongly contest the other party in formal arbitration and testing is required). Additionally, if one or both of you contributed to the contract not completing, then a somewhat generous negotiation by you can will avoid formal arbitration--in which the arbitrator would normally documents at-fault behavior by at-fault parties on their public record.

If any of the above reasons sound interesting to you, then you have nothing to lose by trying Quick Cancellation right now. Just announce that you wish to try it and make an offer on ALL of the below items to the other party:
  1. How much of the funds remaining in escrow should the worker receive? ($ amount?)
  2. Who will receive copyrights to the deliverables? (Employer, Worker, or Split?)
  3. Who agrees to assume the potential 3.5% cancellation fee? (This occurs when the employer opts for a refund, rather than reusing the funds onsite on another worker). (Employer, Worker or Covered by forfeited expert guarantee?)
Important things to know before you start:
  • You cannot negotiate on ratings, because neither of you would be allowed to rate the other. Instead, I would place a neutral rating on both parties saying "Worker and Employer agreed to self mediate the following without formal intervention by a vWorker.com arbitrator"... followed by what you agreed on the 3 terms above. The arbitration would show up under "self mediated" in your profile.

  • If both of you cannot come to a mutual agreement on all of the above 3 items within 3 days...or if one of you wishes to prematurely end the Quick Cancellation, then we will move on to formal mediation/arbitration. Also, remember that Quick Cancellation is a "one time opportunity" that is only available before formal arbitration starts in earnest. Once we move on, neither of you may "change your mind" and request it again.

  • To prevent a party from abusing Quick Cancellation, you can only choose it on a limited # of projects. The limit is currently either 2 project or 20% of your projects (if you have done more than 10 projects). After you exceed the limit you must go into formal arbitration for further scrutiny.

  • If at any time, vWorker.com learns with 100% certainty that either party was at fault, then vWorker.com cannot in good faith allow the self mediation to continue, since that information would otherwise be hidden from other users of the site (who have a right to know that information). If this occurs, the project will move to formal arbitration, regardless of the wishes of one or both parties.

  • This is a trial program, so the rules may change in the future.


----------------------------------------------------- ---------------------------------------------

scottie05, MOTASH,

Please respond and choose EITHER a) or b ) from the below and add any information required in bold as well.


A) If you want to try self mediation
-----------------------------
If you'd like to try self-mediation, then announce "I wish to try self-mediation" and then answer all 3 questions that I mentioned above. DO NOT bring up any issues about fault. Opting for self-mediation does not obligate you to anything unless both of you choose to agree to the terms. If you see that you cannot come to an agreement, you can later choose to move to formal arbitration. If this is your choice, do not wait for me to respond...the idea is to see if you can quickly negotiate a mutually agreement settlement. If the other party has already indicated they wish to try self-mediation, and you do too...please immediately start negotiating back and forth WITHOUT waiting for me, as you only have 3 business days to come to an agreement.

B) If you don't want to try self-mediation
----------------------------
If you do not want to try self-mediation, then just announce "I wish to move to formal arbitration" and then we will do so. To save time...if you were asked a question above for formal arbitration, please respond to it.

Thanks.


Michele Nisi (vWorker)

P.S. Automated warning about upcoming deadline(s). Employer must respond before Wednesday Sep 14, 2011 9:24:13 AM EDT. Worker must respond before Wednesday Sep 14, 2011 9:24:13 AM EDT. If you can respond sooner, please do so, as it will speed up the arbitration process for both parties. Thanks.
 

 
Date: Friday Sep 9, 2011 12:38:09 PM (Arbitration Response Id: 1,665,735)
From: MOTASH (worker)
To: Michele Nisi (vWorker)  (arbitrator)
CC: scottie05 (employer)
 
Thanks for answering my points,i just wanted to make sure that such point gets reviewed, and i fully respect your arbitration management, and forgive me as it's my first arbitration

I've offered the employer a scenario same to "self mediation" before, so i still accept it, and if the employer accepts too, then it would be the first choice

I'd like to thank you for ack'ing me my options, and i'd like if self mediation failed, that a technical arbitrator reviews the contract,since the terms changed over time through messages, and i believe a neutral judgement for a clear contract is required for both parties
 

 
Date: Friday Sep 9, 2011 1:05:00 PM (Arbitration Response Id: 1,665,757)
From: MOTASH (worker)
To: Michele Nisi (vWorker)  (arbitrator)
CC: scottie05 (employer)
 
sorry i didn't follow the "self mediation" rules correctly

"I wish to try self-mediation"

Q1 answer : i accept 80% ($280)

Q2 answer : copy rights to the employer for the original request, while extra code i did is mine

Q3 answer : i assume the employer to handle cancellation fees(subject to negotiation)
 

 
Date: Friday Sep 9, 2011 1:59:31 PM (Arbitration Response Id: 1,665,805)
From: scottie05 (employer)
To: MOTASH  (worker),Michele Nisi (vWorker)  (arbitrator)
 
1. Developer has admitted the code doesn't work outside his development environment and I do not understand why the arbitration process skips key points *including the posted acceptance criteria, which has not been met*.

2. I thought I had a good working relationship with this developer, but I no longer think so.

3. I do not wish to self-mediate.

4. I do not accept the code as it stands.

5. I do not want intellectual property rights.

6. I am happy to pay a cancellation fee just to get out of this entirely unacceptable situation.

7. I am not happy to accept any of the code as complete as I did not agree to pay for a partial solution. I might have used my discretion to decide otherwise before this arbitration process, but no longer.

8. My acceptance criteria were very clear, considered by me as a binding part of the contract, were published beforehand, accepted by the worker, and not negotiable. If formal arbitration and independent testing are the only way to verify they have not been met, lets proceed down that path.





 

 
Date: Sunday Sep 11, 2011 1:32:00 AM (Arbitration Response Id: 1,666,232)
From: MOTASH (worker)
To: Michele Nisi (vWorker)  (arbitrator)
CC: scottie05 (employer)
 
So, it's clear that the employer refuses "Self Mediation", and i'll comply not to answer the employer until asked to, as requested

as i stated earlier, this arbitration is about contract terms, not project acceptance(which might be a consequence), so i think we should ask for a technical arbitrator to clarify the following points at least from my side

1-if i solely volunteered to add some feature(was not requested by the employer before, nor agreed by both to be a requirement after), that later were a source of trouble to me, does removing such feature break the contract

2-the employer didn't specify a version of MSN,am i obliged to make my application work for ALL versions, noting that MSN is an online setup application, and to my knowledge, there's no means to get earlier versions from download site

3-does deliberately giving a wrong feedback, would be an act giving me the right to break the contract

Thanks in advance

 

 
Date: Monday Sep 12, 2011 8:49:19 AM (Arbitration Response Id: 1,666,867)
From: Michele Nisi (vWorker) (Arbitrator)
To: scottie05 (employer),MOTASH  (worker)
 
scottie05, MOTASH,

Since the two of you didn't agree to self-mediate, we will continue with formal arbitration.

MOTASH,

>>1-if i solely volunteered to add some feature(was not requested by the employer before, nor agreed by both to be a requirement after), that later were a source of trouble to me, does removing such feature break the contract

An arbitration is all about making sure that the contract (which the two of you created) is honored. If either party (or both) breaks the contract, my job as the arbitrator is to enforce the appropriate penalty.

The contract is made up of the following:
  1. All information on the project page (title, description, compatibility, etc.).
  2. All onsite amendments that are agreed to by both parties.
These items are NOT a part of the contract:
  1. Things that a party "meant" to put in the contract but neglected to.
  2. Any amendments allegedly communicated offsite. (These are too easy to fake, where even a professional cannot determine if it's real or a forgery, and thus the communication is not admissible.)
  3. Anything that was not agreed to be done by both parties.
It's important to point out that once you agree to do additional work (even if you do it for free)...it then becomes part of the contract and is also due by the deadline.

So to answer your question, yes removing that featuer would break the contract.

>>2-the employer didn't specify a version of MSN,am i obliged to make my application work for ALL versions, noting that MSN is an online setup application, and to my knowledge, there's no means to get earlier versions from download site

That is something a technical arbitrator would need to rule on.

>>3-does deliberately giving a wrong feedback, would be an act giving me the right to break the contract

That would be something a technical arbitrator would review. When you start to allege that someone deliberately gave wrong feedback you get into a difficult area. It is very difficult to prove anyone's intentions on the site. How can we know if someone did something "deliberately"?

Can you give me a brief/specific list of the items that you aren't sure about?
Michele Nisi (vWorker)

P.S. Automated warning about upcoming deadline(s). Worker must respond before Thursday Sep 15, 2011 8:49:19 AM EDT. If you can respond sooner, please do so, as it will speed up the arbitration process for both parties. Thanks.
 

 
Date: Monday Sep 12, 2011 9:01:23 AM (Arbitration Response Id: 1,666,870)
From: scottie05 (employer)
To: MOTASH  (worker),Michele Nisi (vWorker)  (arbitrator)
 
Attached File
0.17 MB

And please do not send me emails like this. Let's keep communication strictly within the structure of the arbitration. We have not communicated via email before, and arbitration is not the place to start.

 

 
Date: Monday Sep 12, 2011 1:12:48 PM (Arbitration Response Id: 1,667,208)
From: MOTASH (worker)
To: Michele Nisi (vWorker)  (arbitrator)
CC: scottie05 (employer)
 
So, point 2,3 are left to the technical arbitrator

while for point 1, of course i take the arbitrator word as final/non-negotiable but i want to make sure that my question is well understood:
* i was not talking about a "employer ask/worker agree or vice versa" scenario, actually i was talking about a sole action(not agreed/confirmed by both parties), as your reply make me wonder that:
a- i may modify the contract terms as i wish by similar sole actions
b-how can completion be judged on such features, that was not stated/agreed in a written way(doesn't include "meant" to be)

in specific words : i believe point First\b in my post on Monday Sep 5, 2011 10:39:42 PM EDT is subject to ask/agree scenario so it's part of the contract, while First\a on the same post, was a sole action(i understand that this may be a decision of the tech arbitrator too),plz advice

thanks in advance
 

 
Date: Tuesday Sep 13, 2011 11:17:25 AM (Arbitration Response Id: 1,667,761)
From: Michele Nisi (vWorker) (Arbitrator)
To: scottie05 (employer),MOTASH  (worker)
 
Motash,

If you offer to do something, unless the employer specifically asks you not to do it, then it is included in the contract.

Can you give me a brief/specific list of the items that you aren't sure about?

Michele Nisi (vWorker)
 

 
Date: Thursday Sep 15, 2011 10:24:46 AM (Arbitration Response Id: 1,668,862)
From: Michele Nisi (vWorker) (Arbitrator)
To: scottie05 (employer),MOTASH  (worker)
 
MOTASH,

By not responding with the information requested, you are now in default of your Worker contract which states: Worker agrees to be prompt in corresponding with Employer and Exhedra. Should a Worker not respond to Exhedra arbitration communication in 3 days, they will forfeit arbitration (at Exhedra's sole discretion). Should a Worker respond in 3 days but (in Exhedra's sole determination) attempt to stall the arbitration by inadequately addressing one or more issues, then they may also be ruled in forfeit of the arbitration (at Exhedra's sole discretion).

The fairest arbitration decisions occur when both sides fully present their version of events. For that reason only, it is site policy to grant one (but ONLY ONE) extension.

Please provide all the information previously requested in 3 business days so that arbitration can continue. Site policy does NOT allow for a 2nd extension, so if you do not reply (or do not provide everything previously requested in your reply) then I will be invoking the forfeiture clause in your contract and awarding arbitration to the other party. Your cooperation is greatly appreciated.

Michele Nisi (vWorker)

P.S. Automated warning about upcoming deadline(s). Worker must respond before Tuesday Sep 20, 2011 10:24:46 AM EDT. If you can respond sooner, please do so, as it will speed up the arbitration process for both parties. Thanks.
 

 
Date: Thursday Sep 15, 2011 12:34:12 PM (Arbitration Response Id: 1,669,116)
From: MOTASH (worker)
To: Michele Nisi (vWorker)  (arbitrator)
CC: scottie05 (employer)
 
I don't really understand why VWorker is taking her "sole discretion" as per the worker contract against me for no apparent reason,i didn't break the 'NORMAL' 3 days response time limit, and there's no single indication that i'm "STALLING"the progress of arbitration, i can only think of two reason you may have considered to have that decision that i'm 'stalling' , and forfeit my right of one extension

A- i'm being late in my responses to the latest extent"3 days": following a record of my response time
"from" "From Time Stamp" "Reply Time Stamp" "Response Time"
Ian Ippolito 9-6-11 10:16 AM 9-6-11 10:16 AM 0:00:52
scottie05 9-6-11 11:57 AM 9-6-11 2:15 PM 2:17:45
scottie06 9-6-11 5:36 PM 9-6-11 6:57 PM 1:20:49
Michele Nisi 9-7-11 11:25 AM 9-7-11 12:06 PM 0:41:02
Michele Nisi 9-8-11 11:46 AM 9-8-11 1:31 PM 1:44:57
Michele Nisi 9-9-11 9:24 AM 9-9-11 12:38 PM 3:13:56
scottie05 9-9-11 1:59 PM 9-11-11 1:32 AM 35:32:29
Michele Nisi 9-12-11 8:49 AM 9-12-11 1:12 PM 4:23:29

for sometimes i almost replied immediately, but after all an average of 6hours response time, so i'm taking only 16% of the normal allowed time(64 hours)
and for only this time, when i had some personal issues that made me busy(and may last for some months later), and take 2 days ( less than 3days) you are forfeiting my right of ONE extension

2- on my post id 1,666,232 dated Sunday Sep 11, 2011 1:32:00 AM , self motivated i posted a clear/specific 3 points, 2 of them will be discussed with the technical arbitrator(as per you said),while the first is still under my discussion with you
but you kept asking for "Can you give me a brief/specific list of the items that you aren't sure about?" on your response ids 1,666,867 and 1,667,761
if the above mentioned 3points are not BRIEF/SPECIFIC LIST OF ITEMS what else would it be ?????

If you have any other indication of stalling from my side plz state it

while in reply for your original response on Tuesday Sep 13, 2011 11:17:25 AM :-
you are stating something i never seen like in my life, you're forfeiting the employer right, by considering acknowledgment as acceptance/agreement, the only known procedure close is giving the employer a REASONABLE time frame to agree/disagree within, and if that time frame is expired after then the acknowledgment can be seen as accept/agree
So Mr/Mrs Arbitrator, what is the time frame given to the employer, and what part of the work agreement(if any) supports your statement
the only part i see relevant is :
"2-All onsite amendments that are agreed to by BOTH parties." and NOT
"1-Things that a party "meant" to put in the contract but neglected to."
which contradicts to your statement


Finally i ask your reply for
First : why i forfeited my one extension, based on unjustified "sole discretion"
Second : your reply for point 1,that is being under our discussion

and after all i'm asking to get in contact with your superior arbitrator/facilitator/...
 

 
Date: Thursday Sep 15, 2011 12:39:07 PM (Arbitration Response Id: 1,669,119)
From: MOTASH (worker)
To: Michele Nisi (vWorker)  (arbitrator)
CC: scottie05 (employer)
 
correction: the normal response time is 3 days which is 72 hours not 64, which makes may average response time is only 8% of normal allowable time

forgive me i might have been a little bit nervous, due to my feeling of some sort of bias, but after all the mathematical mistake was in my favour
 

 
Date: Thursday Sep 15, 2011 1:44:13 PM (Arbitration Response Id: 1,669,165)
From: MOTASH (worker)
To: Michele Nisi (vWorker)  (arbitrator)
CC: scottie05 (employer)
 
Attached File
0.01 MB

attached is the excel sheet of my response time calculations, case the table is not viewed correctly without tabs
 

 
Date: Friday Sep 16, 2011 8:04:00 AM (Arbitration Response Id: 1,669,409)
From: Michele Nisi (vWorker) (Arbitrator)
To: scottie05 (employer),MOTASH  (worker)
 
MOTASH,

Let me back up a second and remind you that you don't have to calculate your average response times or provide any other information like. I understand you may just be cautious about being in arbitration but you shouldn't be that worried about it.

The contract states that each party has 3 business days to respond to the arbitrator and provide the specific information asked for. That means that if you are asked for something, post a response but the response doesn't answer what you are asked for, then you still have not responding on time.

The message you received (about the extension) is a general message that any user, that gets an extension, will receive. It isn't altered for your specific response time/situation.

Basically a user will get the one-time extension if the arbitrator does not think you were intentionally stalling. That is what is meant by "sole discretion." So if the arbitrator (me) thought you were intentionally stalling, you would not have received the one-time extension.


>>I don't really understand why VWorker is taking her "sole discretion" as per the worker contract against me for no apparent reason,i didn't break the 'NORMAL' 3 days response time limit, and there's no single indication that i'm "STALLING"the progress of arbitration, i can only think of two reason you may have considered to have that decision that i'm 'stalling' , and forfeit my right of one extension

I asked you for specific information in Monday Sep 12, 2011 8:49:19 AM (Arbitration Response Id: 1,666,867) which meant you had to respond by Thursday Sep 15, 2011 8:49:19 AM. You posted something but it wasn't clear if that was your final response.

I asked for clarificaition on that but did not hear back. I assume that what you had posted wasn't a full answer to my question. I apologize if I was wrong about that.

If you are saying that what you posted in Monday Sep 12, 2011 1:12:48 PM (Arbitration Response Id: 1,667,208) is
your final response to what you are unsure of, then I will use that as your response.

Is that what you are alleging?

Michele Nisi (vWorker)

P.S. Automated warning about upcoming deadline(s). Worker must respond before Wednesday Sep 21, 2011 8:04:00 AM EDT. If you can respond sooner, please do so, as it will speed up the arbitration process for both parties. Thanks.
 

 
Date: Saturday Sep 17, 2011 12:24:01 AM (Arbitration Response Id: 1,669,871)
From: MOTASH (worker)
To: Michele Nisi (vWorker)  (arbitrator)
CC: scottie05 (employer)
 
ATTN Arbitrator: Michele Nisi
thanks for your clarification

i didn't (calculate my avg response time,clarified that i already answered your question, asked to escalate), for the sake of this arbitration(even if it's affected by its results), but rather that i felt "at that time" that there's some sort of bias towards the other party, so i was negotiating my contract between me(as a client) and you as a vworker representative(service provider),which is even more important than the work contract between me and the employer that is subject to this arbitration

so i kindly ask, if you agree that,a misunderstanding might had happened,and i already had an answer for your question, to undo the extension, else let me escalate the issue and get the employer away from this issue as he's not part of it



ATTN Arbitrator: Michele Nisi , Employer: scottie05

while for the arbitration progress, i just want to clarify the image:-

i stopped working on the project and arbitrated for the previously mentioned 3 reasons(i'll put same reasons just in different order)

1- the employer gave a feedback that a fault in my program based on a test on platforms(64bit) that were not part of the contract, and when i noticed that and faced him, he said that same faults exists on agreed platforms(32bit),but these faults he claimed didn't exist in the data he provided as a feedback
** i see if my allegation in this point is confirmed by the technical arbitrator, then the employer is preventing work from being completed

2-there's unspecified item in the work contract with the employer regarding MSN version, while in normal situation the employer will be asked to specify it, but for the specific case of MSN, i ask the version to be assigned to be available under normal conditions
** this point is needed to reach a project completion (if the project to be resumed), as it's a point of debate with the employer

3-does extra features that i add (mentioned in done/todo items in status reports), are obligatory to me as a part of the contract, even if it was not subject to agreement from both parties(such things are like trials i do, and mentioned in status reports, and with project progress may be later found not to fulfill the requirement so i have to change it to keep progress)
** this point has taken much time for clarification(and may need extra time)

so, while the final decision is yours, i believe the shortest path for resolution of this arbitration is
- the first point is to be judged first, if my claims are true and the employer were found at fault then arbitration done
-else if the employer were not at fault,then point two is judged by the tech arbitrator, and both me and the employer will commit to the decided version
-in the same time, if the third point is subject to clarification/discussion after all i'll commit to the final decision made
 

 
Date: Monday Sep 19, 2011 10:51:32 AM (Arbitration Response Id: 1,670,743)
From: Michele Nisi (vWorker) (Arbitrator)
To: scottie05 (employer)
CC: MOTASH  (worker)
 
MOTASH,

The extension is not going to count against you in this situation. You didn't really need it, if you are telling me that what you posted was the complete answer to what I asked.

Since one (or more) key issues in this arbitration revolve around technical issues in the category of computing, and I am a non-technical arbitrator, I am transferring this arbitration to a technical analyst who specializes in that category. They will resolve all technical amiguities and issues. Thanks for your continued cooperation.

P.S. CHANGE IN EXCUSED ABSENCE NOTIFICATION: To prevent either party from abusing the technical arbitration process, the minimum acceptable advance notification period required to obtain an excused absence is being increased. From this point forward, you must notify the arbitrator in advance a minimum of 1 (one) day for each 1 (one) day of absence. If you know that you have an upcoming absence planned in the near future, you should announce it now. If you don't understand this or have any questions about it, please let your arbitrator know. As a reminder, both of you have agreed in your contracts that Exhedra may make this change: "Exhedra may amend the timeframes of this requirement during the arbitration".
 

 
Date: Monday Sep 19, 2011 10:51:32 AM (Arbitration Response Id: 1,670,744)
From: Michele Nisi (vWorker) (Arbitrator)
To: Tim Yates (vWorker)  (arbitrator)
 
 This message was sent privately

Please provide technical analysis (in the category of computing) on this arbitration..thank you. can you review disputed items?
 

 
Date: Tuesday Sep 20, 2011 11:07:06 AM (Arbitration Response Id: 1,671,372)
From: Tim Yates (vWorker) (Arbitrator)
To: scottie05 (employer),MOTASH  (worker)
 

Diane, Mohamed,

The issue in this arbitration appears to be:

1. Which version of MSN?

Unless the version was specified and agreed to, it would be considered that the latest version would be used.

2. Which environment do the deliverables have to work on?

In Posting # 36,355,035 on Thursday Aug 4, 2011 4:37:24 PM, 64-bit was not required, so the testing environment would have to be 32-bit.

Should the deliverables be tested in arbitration by vWorker, the testing is done to the following requirements (taken from the Employer and Worker's Contract):

2) "Testing Venue:"  Since the deliverables must function in the Employer's environment for acceptance, and the Employer is the party creating the "flaw list", the Employer will be responsible for hosting the testing venue.  However, if the worker is determined to have not released the deliverables in question to the Employer, the Worker will be responsible for hosting the testing venue.  Exhedra does reserves the right to move responsibility for the testing venue to another party if it (in its sole opinion) believes a fairer result may be achieved.  Additionally, Exhedra may choose to host the testing venue itself, if it (in its sole opinion) determines:

a)...that the arbitration venue responsibility would not be better served by either the Employer or the Worker
b)...that significant setup assistance will not be required from the Worker (since a Worker can take advantage of such a situation to do configuration tweaks that were not done on the employer's system)
c)...that it has an existing environment adequate to testing the deliverables

    Both Employer and Worker agree that if required to provide the testing venue, they will provide Exhedra with access to all aspects of their environment that are necessary for Exhedra to:

a) Verify or deny the Employer's claims in the flaw list
b) Verify or deny that deliverables have been modified to cheat the testing process

    Note that these aspects may include (but are not limited to) software, hardware, documentation, remote access to systems etc..   Should the party responsible for hosting the testing venue refuse to provide all aspects of the testing venue when required to, they will default on the arbitration and forfeit it.

     Exhedra may use file comparisons (and/or other means) to ensure that modification of deliverables does not occur by the testing venue host.  If Exhedra (in its sole judgment) determines that the host has modified deliverables to influence an arbitration unfairly in their favor, the host will forfeit arbitration, be found in default of their contract under the terms of 'fraud', and will have their account involuntarily closed.

3. Are extra features added by the worker considered part of the contract?

This question has already been addressed. The answer is yes.

Mohamed,

You wrote:

1- the employer gave a feedback that a fault in my program based on a test on platforms(64bit) that were not part of the contract, and when i noticed that and faced him, he said that same faults exists on agreed platforms(32bit),but these faults he claimed didn't exist in the data he provided as a feedback
** i see if my allegation in this point is confirmed by the technical arbitrator, then the employer is preventing work from being completed


The employer would have to show that the error existed in the 32 bit version. Please explain how this would prevent you from completing the work. From what I have read, a log was provided from the 32 bit version.

For this feature, are you stating that this feature, MSN (latest version) on a 32 bit version of Windows is complete?


Regards.
Tim Yates (vWorker)



P.S. Automated warning about upcoming deadline(s). Worker must respond before Friday Sep 23, 2011 11:07:06 AM EDT. If you can respond sooner, please do so, as it will speed up the arbitration process for both parties. Thanks.
 

 
Date: Tuesday Sep 20, 2011 10:43:02 PM (Arbitration Response Id: 1,671,651)
From: MOTASH (worker)
To: Tim Yates (vWorker)  (arbitrator)
CC: scottie05 (employer)
 
Mr Tim Yates :
I'd first start with answering the question :
"are you stating that this feature, MSN (latest version) on a 32 bit version of Windows is complete?"
*a newer version of MSN has been released,if project to be resumed i'll check my code against the last version, and if any modifications needs to be done, i'll do it as per my commitment

while for the posted points:-
1. Which version of MSN?
-the latest version,that's clear to me

2. Which environment do the deliverables have to work on?
clear to me,32 bit platforms as per Posting # 36,355,035, but to be more specific as this posting is an extension to Posting # 36,355,031, so specifically i believe its :
ONLY XP SP3, Vista SP1, Windows 7 on 32bit platform

3. Are extra features added by the worker considered part of the contract?
NOT CLEAR, since we are technically speaking,we should not consider a general answer for general request, as it had been subject to clarification and not been answered in its detailed form on Arbitration Response Ids: 1,669,116 , 1,669,871

Finally to clarify the heart of the conflict:
- on my Posting # 36,572,934, i sent a version that was fully accepted by employer except for a crash inside my code that he claims to only happen with a previous version of MSN
- as per our agreement that i can't and not responsible to test every function,to check if that crash really happens inside one of the untested functions that the older version might have called, i added structured exception handling to all functions of my code ,such that when a fault condition happens inside any of my functions, then my structured exception handling (SEH) will log that fault as a [SEH] section inside the log file
- the employer couldn't proof any malfunction inside my code till his Posting # 36,703,242 on Friday Sep 2, 2011 7:16:48 PM, where he claimed that a SEH section found inside the log file, and stated that it happened on 3 different PCs with VISTA , Win7
-i asked for the log file that proofs this on my Posting # 36,703,471 on Friday Sep 2, 2011 7:56:18 PM
- the employer sent proof of my program fault on his attachment (3 log files)to Posting # 36,703,923 on Friday Sep 2, 2011 9:58:11 PM, which all are true to have [SEH] HookDLLApi as per his claim on Posting # 36,703,242 on Friday Sep 2, 2011 7:16:48 PM,( which proofs that my structured exception handling is working and really logs SEH section when fault happens inside my code)
- reviewing the attachments in details i found "c:\Program Files (x86)", so i faced the employer if these results were done on 64bit platform ( which is not part of the contract) on my Posting # 36,704,043 on Friday Sep 2, 2011 10:19:08 PM
- the employer replied with something very strange,
"HE USED THE NEAREST PCs TO REPLICATE THE ERROR WHICH HAPPENS TO BE ALL and i repeat ALL ARE 64BIT",and he insisted that it happens on 32bit
- on his Posting # 36,704,482 on Friday Sep 2, 2011 11:53:18 PM, he attached the 32bit logs(only one file), which had no sign of his claimed SEH fault

so, if the employer is taking advantage of the contract terms that "it must work on his environment", and alleges malfunction which happens on platforms that is not part of the contract,and when discovered by me and been faced with he gives SOME excuse, and still alleging it to happen on the agreed platforms,then the proof he sent have no sign of malfunction as per his claim

so what do you call this Mr Arbitrator, and what part of the contract justifies his actions?
How can work be completed if the employer kept telling things that does not exist(like what happened in this example) in the future?


 

 
Date: Wednesday Sep 21, 2011 12:23:03 PM (Arbitration Response Id: 1,672,194)
From: Tim Yates (vWorker) (Arbitrator)
To: scottie05 (employer),MOTASH  (worker)
 
Diane,

In the posting on Posting # 36,704,482 on Friday Sep 2, 2011 11:53:18 PM, you included a log file and in Arbitration Response Id: 1,663,968, you attached an image. What are you stating is the issue on these two posts? I do not see an error in either the log or the image.

Mohamed,

You wrote:

NOT CLEAR, since we are technically speaking,we should not consider a general answer for general request, as it had been subject to clarification and not been answered in its detailed form on Arbitration Response Ids: 1,669,116 , 1,669,871

The issue in arbitration response id: 1,669,116 and 1,669,871 that concern the deadline response was already addressed by Michele in Arbitration Response Id: 1,670,743. You do not need to bring this up again.

so, if the employer is taking advantage of the contract terms that "it must work on his environment", and alleges malfunction which happens on platforms that is not part of the contract,and when discovered by me and been faced with he gives SOME excuse, and still alleging it to happen on the agreed platforms,then the proof he sent have no sign of malfunction as per his claim

so what do you call this Mr Arbitrator, and what part of the contract justifies his actions?
How can work be completed if the employer kept telling things that does not exist(like what happened in this example) in the future?


I believe that the employer is stating that there is a different issue on the 32 bit and I have asked for clarification.


Regards.
Tim Yates (vWorker)

P.S. Automated warning about upcoming deadline(s). Employer must respond before Monday Sep 26, 2011 12:23:03 PM EDT. If you can respond sooner, please do so, as it will speed up the arbitration process for both parties. Thanks.
 

 
Date: Wednesday Sep 21, 2011 2:51:50 PM (Arbitration Response Id: 1,672,263)
From: scottie05 (employer)
To: Tim Yates (vWorker)  (arbitrator)
CC: MOTASH  (worker)
 
Whether or not the log contains an error is irrelevant to the spec. The error was something the developer added for troubleshooting purposes.

The application should log considerably more information than the start and end events. It should log all calls to the winsock library mentioned in the spec. For MSN Live, simply logging in and sending one message generates about 50-70 winsock calls, all of which should be present in the log.

Steps to replicate:

1. Install a clean Windows 7 32 bit environment.
2. Download and install the latest version of MSN Live/Messenger (from memory, 15.4 I believe).
3. Close MSN Live messenger if it is running.
4. Launch the tool with the arguments shown in the screenshot, to launch MSN live messenger.
5. Login to MSN Live messenger with valid credentials.
6. Contact another MSN messenger account and send a test: "This is a test message -- please ignore".
7. Close MSN Live messenger.
8. Open the log and examine the entries.

Expected behavior:

Log should contain the [start] entry and several dozen intermediate entries, including GetAddrInfo (host name lookups) SEND/RECV entries and many more. After about 70 or so entries, the log should finish with an [End] entry.


Observed behavior:

Log contains only the [start] and [end] entries and no information in between.

Evidence:
See screenshot uploaded 1,663,968,


Notes:

One test did take place on a 64 bit environment. When the developer pointed this out, I was reminded that the product spec ruled out x64 and no further 64 bit tests were conducted. Instead several 32 bit tests were conducted, each resulting in an empty log (except for the start and end information).

I have not yet seen this product, in any revision, successfully log the required information for MSN messenger. Earlier versions logged more, with the supposed final version logging only start/end information.

We tested on several versions of MSN to give the developer more information to work with, not to "require" that they all work. As I've said, if the toolkit logs data on one version of MSN consistently, regardless of which, it would have been acceptable. We have not yet had found it to work on ANY version of MSN on ANY platform.

Our test environments are simple and standardized: A clean, 32-bit install of XP or Windows 7 with the latest updates/patches, and the latest version of MSN live. No additional tools, security features, or anything else to interfere wit the code.




 

 
Date: Wednesday Sep 21, 2011 3:12:01 PM (Arbitration Response Id: 1,672,270)
From: scottie05 (employer)
To: Tim Yates (vWorker)  (arbitrator)
CC: MOTASH  (worker)
 
Attached File
0.04 MB

To clarify the previous post, here is an example of what should be contained in the log, taken from an earlier version.

In the final version, this information was not present.

As can be seen, there is considerably more than start and end information.

The version shown in the log is irrelevant, as it is included only as an example of what should be present in the file. Neither the version shown nor any other version tested, including the latest, logs anything other than start and end.

 

 
Date: Thursday Sep 22, 2011 11:38:24 AM (Arbitration Response Id: 1,672,828)
From: Tim Yates (vWorker) (Arbitrator)
To: scottie05 (employer),MOTASH  (worker)
 

Mohamed,

Given the employer's response, I see no indication that they are withholding information from you, so they would not be found at fault for preventing you from completing the work.

As the project is in an implicit deadline, do you believe this work to be 100% complete? If so, I will be able to test the work.

If the work is not 100% complete, what work remains to be completed?

Regards.
Tim Yates (vWorker)



P.S. Automated warning about upcoming deadline(s). Worker must respond before Tuesday Sep 27, 2011 11:38:24 AM EDT. If you can respond sooner, please do so, as it will speed up the arbitration process for both parties. Thanks.
 

 
Date: Saturday Sep 24, 2011 7:33:51 PM (Arbitration Response Id: 1,674,039)
From: MOTASH (worker)
To: Tim Yates (vWorker)  (arbitrator)
CC: scottie05 (employer)
 
Tim,

A-Regarding your questions:
as i stated earlier, a new version of MSN is released,
the work remain to be completed:
- installing latest version and testing against it
- if necessary, doing modifications to make it work(and i have no idea right now, what exact modifications ,if any, are required)


B-while for "extra features":
arbitration response id: 1,669,116 and 1,669,871 also addresses this issue,and not yet replied
kindly find a complete history of that question and replies,in my following arbitration response, as this point is not yet cleared


C-Finally, regarding employer feedback :
as a judging party,i expect you not to follow nor show what you THINK on behalf of any party, until BOTH parties show their allegations(you did so on arbit. resp. ID: 1,672,194 before the employer gave his reply)

The employer response had many irrelevant and contradicting points that i have to address:-

1-"Whether or not the log contains an error is irrelevant to the spec"
My Reply:that's not true, any agreed details by both parties in their conversation is part of the specs, and I'M SURPRISED THAT YOU DIDN'T REPLY HIM

2-most of the employer response ignored the fault, subject to your question,and addresses how much log should contain,and how to test
My Reply: as you can see through our conversation, before the employer broke the contract terms by testing on disagreed platforms and tried to commit me to it,the work was progressing forward and the employer was fully satisfied,please refer to my below NOTE1 for evidence

3-a relevant employer reply "One test did take place on a 64 bit environment. When the developer pointed this out, I was reminded that the product spec ruled out x64 and no further 64 bit tests were conducted"
My Comment: as per our work agreement, i'm committed to make my work running on the employer environment, then the employer Posting # 36,703,242 on Friday Sep 2, 2011 7:16:48 PM is committing me to address that fault,in which,i insist, he broke the contract terms by using an 64bit environment, and to me breaking the terms once, is like twice or more and after all it's what he says

4- also regarding employer:"One test did take place on a 64 bit environment. When the developer pointed this out, I was reminded that the product spec ruled out x64 and no further 64 bit tests were conducted"
My Reply: the employer here is justifying the test on 64bit, that he was reminded, as if he FORGOT the terms, while in his Posting # 36,704,391, he justifies it by "the most convenient PC on which to re-generate the logs",so which excuse should i believe?

NOTE1: employer feedback regarding Project Progress

Posting # 36,383,974 on Sunday Aug 7, 2011 12:34:22 PM: "Excellent work so far. I'm glad to see you are already past the preliminary stages of dll injection"

Posting # 36,464,432 on Saturday Aug 13, 2011 11:44:01 AM : "Thanks for the update.Sounds like you are doing some cutting-edge work"

Posting # 36,524,174 on Thursday Aug 18, 2011 10:23:16 AM: "I evaluated everything against Windows Live Messenger and it looks good"

Posting # 36,556,198 on Sunday Aug 21, 2011 10:37:25 AM : "I'm very happy with your work so far, and value what you are building for us"

Posting # 36,581,108 on Tuesday Aug 23, 2011 11:55:56 AM : "Excellent work so far. I've been able to generate meaningful logs on IE and other browsers" , "I'm very pleased with progress, and I am assigning another week to give you time to clean up/finalize"

** from this posting, as per his words "The crash in my version of MSN Live/ Messenger is a concern",the employer kept committing me to his results on an older version of MSN that i could not be able to install on MY PC, , so i didn't commit my self to his version, but to my best in good faith i did trials (some of which were unsuccessful,since they were blind) addressing if any fault inside my code, the only occurrence of fault inside my code and on a new MSN version was his claim on Posting # 36,703,242, which on his Posting # 36,704,391 stated was on 64bit and all OS's "The last set of tests was on a 64bit OS (the most convenient PC on which to re-generate the logs) -- but it happens on all OSes. I will upload the logs from the other (32 bit) PC shortly.", but he failed to regenerate it on 32bit

 

 
Date: Saturday Sep 24, 2011 7:46:58 PM (Arbitration Response Id: 1,674,041)
From: MOTASH (worker)
To: Tim Yates (vWorker)  (arbitrator)
CC: scottie05 (employer)
 
Note: 1 long word(s)/URL(s) in this posting > 65 characters was/were broken up with spaces to prevent it/them from stretching the screen and making it difficult to read.

"Extra Features", question flow between me and Michele :



Me on Arbitration Response Id: 1,666,232 :
"1-if i solely volunteered to add some feature(was not requested by the employer before, nor agreed by both to be a requirement after), that later were a source of trouble to me, does removing such feature break the contract"



Michele on Arbitration Response Id: 1,666,867 :
"It's important to point out that once you agree to do additional work (even if you do it for free)...it then becomes part of the contract and is also due by the deadline.So to answer your question, yes removing that featuer would break the contract."



Me on Arbitration Response Id: 1,667,208 :
"while for point 1, of course i take the arbitrator word as final/non-negotiable but i want to make sure that my question is well understood:
* i was not talking about a "employer ask/worker agree or vice versa" scenario, actually i was talking about a sole action(not agreed/confirmed by both parties), as your reply make me wonder that:
a- i may modify the contract terms as i wish by similar sole actions
b-how can completion be judged on such features, that was not stated/agreed in a written way(doesn't include "meant" to be)
in specific words : i believe point First\b in my post on Monday Sep 5, 2011 10:39:42 PM EDT is subject to ask/agree scenario so it's part of the contract, while First\a on the same post, was a sole action(i understand that this may be a decision of the tech arbitrator too),plz advice"



Michaele on Arbitration Response Id: 1,667,761 :
If you offer to do something, unless the employer specifically asks you not to do it, then it is included in the contract.



Me on Arbitration Response Id: 1,669,116 :
"you are stating something i never seen like in my life, you're forfeiting the employer right, by considering acknowledgment as acceptance/agreement, the only known procedure close is giving the employer a REASONABLE time frame to agree/disagree within, and if that time frame is expired after then the acknowledgment can be seen as accept/agree
So Mr/Mrs Arbitrator, what is the time frame given to the employer, and what part of the work agreement(if any) supports your statement,the only part i see relevant is :
"2-All onsite amendments that are agreed to by BOTH parties." and NOT
"1-Things that a party "meant" to put in the contract but neglected to."
which contradicts to your statement"
"Second : your reply for point 1,that is being under our discussion"



Michele No Reply regarding the question



Me on Arbitration Response Id: 1,669,871 :
"3-does extra features that i add (mentioned in done/todo items in status reports), are obligatory to me as a part of the contract, even if it was not subject to agreement from both parties(such things are like trials i do, and mentioned in status reports, and with project progress may be later found not to fulfill the requirement so i have to change it to keep progress)"



Michele No Reply regarding the question

------------------------------------------------------ --------------------------------

Tim Yates on Arbitration Response Id: 1,671,372 :
returning me to point zero
 

 
Date: Monday Sep 26, 2011 2:56:06 PM (Arbitration Response Id: 1,674,883)
From: Tim Yates (vWorker) (Arbitrator)
To: scottie05 (employer),MOTASH  (worker)
 
Mohamed,

You wrote:

My Reply:that's not true, any agreed details by both parties in their conversation is part of the specs, and I'M SURPRISED THAT YOU DIDN'T REPLY HIM

and

as a judging party,i expect you not to follow nor show what you THINK on behalf of any party, until BOTH parties show their allegations(you did so on arbit. resp. ID: 1,672,194 before the employer gave his reply)

I would like to remind  you to remain professional in your comments, do not use caps (shouting) and refrain from giving personal opinions. Further opinions will be grounds for forfeiting the arbitration, so please take care in your responses.

Regards.
Tim Yates (vWorker)
 

 
Date: Monday Sep 26, 2011 3:26:55 PM (Arbitration Response Id: 1,674,901)
From: MOTASH (worker)
To: Tim Yates (vWorker)  (arbitrator)
CC: scottie05 (employer)
 
Tim,

actually using caps is the only way i know to catch attention(is html tags to highlight/bold,..allowed?), on the other hand i don't know of literature/terms/... that makes CAPS -> "shouting" ,

"There are however situations where further capitalization may be used to give added emphasis"
Wikipedia :
http://en.wikipedia.org/wiki/Letter_case

So i hope no offense be taken, as it never meant to be that way



while, what i said referring to your arbit. resp. ID: 1,672,194 is not an opinion, actually it's a request for a blind neutral judgement



i hope i cleared my behavior, and looking forward to having your reply

Regards,
MOTASH

 

 
Date: Monday Sep 26, 2011 3:57:24 PM (Arbitration Response Id: 1,674,916)
From: Tim Yates (vWorker) (Arbitrator)
To: scottie05 (employer),MOTASH  (worker)
 

Diane, Mohamed,

Mohamed has claimed previously that the employer is preventing work from being completed.

After looking at the evidence, this does not appear to be the case, so the project will go forward.

Project Status

At this point in time, the project is in an "implicit deadline" meaning that work is to continue. The original deadline expired, and work continued without a new deadline being set. In order for work to continue, what needs to be determined is:

1. What is the remaining work to be completed?
2. Is there anything being requested that is not part of the contract.
3. A new deadline needs to be set.


Mohamed, you wrote:

C-Finally, regarding employer feedback :
as a judging party,i expect you not to follow nor show what you THINK on behalf of any party, until BOTH parties show their allegations(you did so on arbit. resp. ID: 1,672,194 before the employer gave his reply)

I was responding to your question only. You were asking my opinion and I gave it.

The employer response had many irrelevant and contradicting points that i have to address:-

Please note that Michele asked in Arbitration Response Id: 1,664,366 not to respond to the other person's posts. This restriction is still in effect.

B-while for "extra features":
arbitration response id: 1,669,116 and 1,669,871 also addresses this issue,and not yet replied
kindly find a complete history of that question and replies,in my following arbitration response, as this point is not yet cleared


I am unclear from your response and the responses in those ids what you are stating is an extra feature.

Please state exactly what you consider to be extra features that you believe that you do not have to complete. I do not need you to refer to other posts in the arbitration. Just state what you believe to be not part of the contract.

Mohamed,

Your previous responses contain many points and issues and it was very difficult to determine what your questions were. I do not want to miss legitimate questions, but your reponse makes it difficult to determine what those questions are. Long postings like this delay the arbitration. Please keep your responses short and on the topic that needs to be addressed.


Regards.
Tim Yates (vWorker)



P.S. Automated warning about upcoming deadline(s). Worker must respond before Thursday Sep 29, 2011 3:57:24 PM EDT. If you can respond sooner, please do so, as it will speed up the arbitration process for both parties. Thanks.
 

 
Date: Monday Sep 26, 2011 5:05:59 PM (Arbitration Response Id: 1,674,936)
From: MOTASH (worker)
To: Tim Yates (vWorker)  (arbitrator)
CC: scottie05 (employer)
 
Tim,

i didn't break Michele request,"not to respond to employer", actually you wrote"Given the employer's response",which makes employer response implied in your statement, so technically i was responding to you
So, at least points (1,3,4) must be answered, as you based your judgment on this employer response

i apologize for long posting, For Now, plz forget about any previous questions, i'll give a short direct simple numbered questions:

1- when the employer gives a feedback about a test on his environment, are the results he submits on the site obligatory to me or not?
2-the employer admitted to do test on 64bit platform and posted the results on the site,which as you know ,clearly is not part of the contract, is that his right or a mistake/fault?
3-if the employer gave me incorrect test feedback, wouldn't that prevent me from finishing work?

kindly, answer these questions ASAP, to be able to respond to your question(if still needed) within 3days

Regards,
MOTASH
 

 
Date: Monday Sep 26, 2011 6:04:25 PM (Arbitration Response Id: 1,674,946)
From: scottie05 (employer)
To: Tim Yates (vWorker)  (arbitrator)
CC: MOTASH  (worker)
 
In post # 36,728,332 the worker states that he gives up.

The project was marked as complete. It was not working satisfactorily.

Are you saying my only choice was to extend the deadline, even though the work was already late and not in an acceptable condition?
 

 
Date: Tuesday Sep 27, 2011 1:24:52 PM (Arbitration Response Id: 1,675,414)
From: scottie05 (employer)
To: MOTASH  (worker),Tim Yates (vWorker)  (arbitrator)
 


No indication that the arbitration is complete has been made anywhere in the project thread, although I have to assume that, at this point, it is, according to Arbitration Response Id: 1,674,916. that rules in my favor.



i've received no answer to my subsequent question, so I have assumed arbitration is complete and I am re-commencing working with the worker.



The additional 3 weeks (almost) spent in arbitration (with funds tied up) was significantly damaging to us, as the delivery dealine to our client now only 4 days away, leaving us no room for error or adjustment. 



Because of this, we can only grant an additional 24 hours to deliver the final working project, to be delivered with a message that lets me clearly understand it has been delivered (with no arguments, accusations or other topics that make it unclear what the worker is delivering). 



I expec the final delivery to be testable and working on the latest versions of the products listed in the spec.  There has been no new release of MSN Live messenger since May 2011, and this is the version I expect it to work with.



I do not expect anything in addition to the original spec, but neither will I accept partially complete.



I am ignoring anything the worker has posted since putting the project into arbitration as I am unable to determine what exactly constitutes final delivery, or if it has actually occurred.



That's all I can do to get the project back on track, and I think I am being reasonable under the circumstances.



 



 



 


 

 
Date: Tuesday Sep 27, 2011 3:53:48 PM (Arbitration Response Id: 1,675,506)
From: Tim Yates (vWorker) (Arbitrator)
To: scottie05 (employer),MOTASH  (worker)
 

Motash,

Thank you for your response. Your questions are much clearer. My responses are below.

1- when the employer gives a feedback about a test on his environment, are the results he submits on the site obligatory to me or not?

Yes, as long as the results were part of the contract.

2-the employer admitted to do test on 64bit platform and posted the results on the site,which as you know ,clearly is not part of the contract, is that his right or a mistake/fault?

Since the results for that test were not part of the contract (64 bit), that would not be held against you. You brought it to Diane's attention and other tests were run.

3-if the employer gave me incorrect test feedback, wouldn't that prevent me from finishing work?

If you brought the issue to their attention and they submitted tests in the 32 bit environment, then they did not prevent you from completing the work. If the situation were reversed, you did testing on a 64 bit computer and the employer pointed it out and then you changed environments, they could not claim that the worker could not complete the work.

Again, you would have to prove that they deliberately prevented you from completing the work. I do not see that here.

Regards.
Tim Yates (vWorker)

 

 
Date: Tuesday Sep 27, 2011 3:56:02 PM (Arbitration Response Id: 1,675,509)
From: Tim Yates (vWorker) (Arbitrator)
To: scottie05 (employer),MOTASH  (worker)
 
Note: 1 long word(s)/URL(s) in this posting > 65 characters was/were broken up with spaces to prevent it/them from stretching the screen and making it difficult to read.

Diane,

You wrote:

In post # 36,728,332 the worker states that he gives up.

The project was marked as complete. It was not working satisfactorily.

Are you saying my only choice was to extend the deadline, even though the work was already late and not in an acceptable condition?


When the worker misses a deadline, you can either cancel and receive a refund if the project is not 100% complete, or choose to continue to work with them. If you choose to work with them, that is fine...but it is vitally important that you set a new deadline. You were warned in the email notification you received when the project became overdue, that if you continued work but didn't set a new deadline, you would be doing a dangerous thing and would be working without the protection of a deadline. (The reason for this rule, called the “implicit extension” rule, is to protect workers from unscrupulous employers who could use the loophole to get a worker to do all sorts free work, and then retroactively 'cancel' for a deadline missed weeks or months earlier.) If you didn't get a chance to read that email, I recommend that you do so now: http://www.vWorker.com/RentACoder/SoftwareBuyers/Articles/RacEm ails/BuyerNotificationOfDeadlineComing.asp.

Had you actually set a deadline, you would now been in an extremely strong position. A project where the deadline has expired is either 100% complete or isn't. If it isn't 100% complete, then you would receive a full refund. We simply test the project and determine if it's 100% complete or not and then refund your funds. This gives you maximum protection.

However, since you didn't set a new deadline, we can't fairly test for the project being 100% complete on time, when there is no agreement between the two of you as to when the project should be 100% complete. So now if you unilaterally pullout, you would be the one breaking the contract instead of the worker. You would have to pay the worker for the time invested (a partial payment). Additionally a rating notating that you pulled out would have to be put on your record. (Again, if it weren't this way, an unscrupulous employer could use that loophole to get free work out of workers…as described above).

Regards.
Tim Yates (vWorker)

 

 
Date: Tuesday Sep 27, 2011 4:06:31 PM (Arbitration Response Id: 1,675,530)
From: Tim Yates (vWorker) (Arbitrator)
To: scottie05 (employer),MOTASH  (worker)
 

Motash,

Please respond to Diane's request in Arbitration Response Id: 1,675,414. Can you complete the work by this time, if not, please propose a new deadline.

Diane,

You wrote:

i've received no answer to my subsequent question, so I have assumed arbitration is complete and I am re-commencing working with the worker.

Arbitration is not yet complete, as a deadline is not agreed upon.

Also, I do not see where you have posted a question. Please let me know what the issue might be.

Regards.
Tim Yates (vWorker)



P.S. Automated warning about upcoming deadline(s). Employer must respond before Friday Sep 30, 2011 4:06:31 PM EDT. Worker must respond before Friday Sep 30, 2011 4:06:31 PM EDT. If you can respond sooner, please do so, as it will speed up the arbitration process for both parties. Thanks.
 

 
Date: Tuesday Sep 27, 2011 5:49:32 PM (Arbitration Response Id: 1,675,592)
From: MOTASH (worker)
To: Tim Yates (vWorker)  (arbitrator)
CC: scottie05 (employer)
 


Tim,



Q: Can you complete the work by this time, if not, please propose a new deadline?



Answer : of course 24hrs is not accpetable, and while i was thinking if i'm obliged to put a deadline right now without further investigation/effort that i believe i shouldn't do till this arbitration is finished, actually the employer already took action and put a deadline on the project with 24 hours, which makes me confused



1- what should i do, should that be neglected on the project panel, or does it have any further consequences if the project is resumed?



2- "does he has the right to do that?" as per work contract,who's given authorization to put a deadline when the project is in "implicit extension" state ?



 



while for my questions :



i really thank you for the clear reply, on my behalf i'll keep short/focused and respond as fast as i can



Q1: is quite clear,while for Q2,Q3, i think you addressed only one aspect " that i'm not obliged neither to (q2)unagreed conditions nor to (q3)wrong feedback" , but other aspects are:-



1- Responsibility : you made the employer completely not responsible for either faults ( Q2 ,Q3)



2- Time : puting in mind that his feedback is by default committing me, who count for the time needed to detect if the the test was done on agreed platform or not (luckily me, i could find program files(x86) to assume 64bit)



3- Effort : i don't get paid, to get employer faults



 



Regards,



MOTASH


 

 
Date: Wednesday Sep 28, 2011 2:05:14 PM (Arbitration Response Id: 1,676,104)
From: Tim Yates (vWorker) (Arbitrator)
To: scottie05 (employer),MOTASH  (worker)
 

Motash,

If you need more time, then you need to propose a new deadline. As this project is in arbitration, I would determine the new deadline based on the feedback from you and the employer.

Q1: is quite clear,while for Q2,Q3, i think you addressed only one aspect " that i'm not obliged neither to (q2)unagreed conditions nor to (q3)wrong feedback" , but other aspects are:-

1- Responsibility : you made the employer completely not responsible for either faults ( Q2 ,Q3)

The employer gave additional feedback regarding the work. This did not prevent you from completing the work.

2- Time : puting in mind that his feedback is by default committing me, who count for the time needed to detect if the the test was done on agreed platform or not (luckily me, i could find program files(x86) to assume 64bit)

The project is in an implicit deadline. Again, using the employer using the 64 bit version of Windows did not prevent you from completing the work and the employer also raised the issue with the 32 bit version.

3- Effort : i don't get paid, to get employer faults

You will get paid if you complete the work.

This project came into arbitration to resolve a contract dispute. You did not state when this project initially came into arbitration that the employer was preventing you from completing the work. Furthermore, continuing to bring up this issue also delays the arbitration. The decision has been made in this regard. No further discussion is warranted.

Q1 Answer : the employer asked to inject a logger DLL into the process of three executables (MSN , IE v8 , Chrome v12), so i got it working for the three programs, and after i sent him the code and log proofs,he asked for a solution for an older version of MSN that's not available,in a good faith i tried to investigate the issue, but MSN is an online setup, and that version is not available,i asked if he has an installable source for it,but never had a reply,and i commit to the original open post, that i've already fulfilled

Q2 Answer : a proof of MSN logging success exists in the attachment sent on "Monday Aug 22, 2011 10:17:07 PM EDT" path in compressed file : \IMCATRUN\DEBUG\test.log


The version of MSN, the issue with MSN,  and the version of Windows has been clarified in this arbitration. All that remains is for a new deadline to be set. If one cannot be agreed upon, I will impose the deadline.

Motash,

Please offer a new deadline to complete the work. I have not changed the deadline for responding as I am still asking for the same information.

Regards.
Tim Yates (vWorker)

 

 
Date: Thursday Sep 29, 2011 4:14:12 PM (Arbitration Response Id: 1,676,769)
From: vWorker Agent (vWorker ) (Arbitrator)
To: scottie05 (employer)
 
 This message was sent privately

Diane Pither-Patterson,

This is an automated reminder that the deadline for your response on this arbitration is less than a day away and your mediator/arbitrator has not yet received your response. (If you HAVE already responded then please ignore the rest of this message as it has simply 'crossed in the mail' with your response). vWorker.com does not like to see any party forfeit, so we are warning you that you need to respond before 9/30/2011 4:06:31 PM EDT to avoid doing so (per your contract). Once you respond, your mediator/arbitrator will be able to take 'your side of the story' into account in the hearing.

(IMPORTANT: If you had to respond to a flaw list, you must click 'I am Finished' when you are done. If you do not, your response will be incomplete and you will forfeit for non-response.)

Thank you,
vWorker.com automated reminder
 

 
Date: Thursday Sep 29, 2011 4:39:52 PM (Arbitration Response Id: 1,676,775)
From: scottie05 (employer)
To: MOTASH  (worker),Tim Yates (vWorker)  (arbitrator)
 


The question was about the deadline, which you answered in your previous response.


 

 
Date: Friday Sep 30, 2011 5:09:45 AM (Arbitration Response Id: 1,676,926)
From: MOTASH (worker)
To: Tim Yates (vWorker)  (arbitrator)
CC: scottie05 (employer)
 
Attached File
0.42 MB

Note: 2 long word(s)/URL(s) in this posting > 65 characters was/were broken up with spaces to prevent it/them from stretching the screen and making it difficult to read.

Tim,


You don't see my previous reply as an answer, and the employer action of setting a deadline on the project is irrelevant
Well,to answer your question :-


A-There's a bug/incompatability with latest MSN, that makes its setup on my PC not possible for the moment,to explain :
while trying to replicate the crash problem, that is claimed by employer,i removed my version, and gave trials, but failed to get a version 14x installation, and from since i'm not able to setup latest MSN again(the setup logs attached proofs setup errors from 6-9-2011), forced by your post to impose a deadline, i searched for that error, and found many people suffering from the same problem,and some replies on MSN Blogs, indicate a bug in latest version  twords OS language options, a link :
http://windowsteamblog.com/windows_live/b/windowslive/archive /2010/08/17/windows-live-essentials-2011-beta-refresh.aspx
to send you a formal reply from MS, i sent a question to Win Live Solutions center(PDF attached), and waited to the last minute,but yet had no reply, so i think this situation is subject to "Setup program bug items" , an adequate deadline is " 5 days from a fix is provided"

B-Since a decision is made that i address only latest MSN version, a consequence is that XP is excluded form test OS's for MSN, as latest MSN doesn't support XP,kindly check :
http://explore.live.com/windows-live-essentials-programs-didnt -install-ui


while there's some points, irrelevant to the employer ,concerning the arbitration process,i will have to discuss in a separete posting

 

 
Date: Friday Sep 30, 2011 5:23:38 AM (Arbitration Response Id: 1,676,928)
From: MOTASH (worker)
To: Tim Yates (vWorker)  (arbitrator)
CC: scottie05 (employer)
 
Attached File
0.42 MB

Note: 2 long word(s)/URL(s) in this posting > 65 characters was/were broken up with spaces to prevent it/them from stretching the screen and making it difficult to read.

Tim,


You don't see my previous reply as an answer, and the employer action of setting a deadline on the project is irrelevant
Well,to answer your question :-


A-There's a bug/incompatability with latest MSN, that makes its setup on my PC not possible for the moment,to explain :
while trying to replicate the crash problem, that is claimed by employer,i removed my version, and gave trials, but failed to get a version 14x installation, and from since i'm not able to setup latest MSN again(the setup logs attached proofs setup errors from 6-9-2011), forced by your post to impose a deadline, i searched for that error, and found many people suffering from the same problem,and some replies on MSN Blogs, indicate a bug in latest version  twords OS language options, a link :
http://windowsteamblog.com/windows_live/b/windowslive/archive /2010/08/17/windows-live-essentials-2011-beta-refresh.aspx
to send you a formal reply from MS, i sent a question to Win Live Solutions center(PDF attached), and waited to the last minute,but yet had no reply, so i think this situation is subject to "Setup program bug items" , an adequate deadline is " 5 days from a fix is provided"

B-Since a decision is made that i address only latest MSN version, a consequence is that XP is excluded form test OS's for MSN, as latest MSN doesn't support XP,kindly check :
http://explore.live.com/windows-live-essentials-programs-didnt -install-ui


while there's some points, irrelevant to the employer ,concerning the arbitration process,i will have to discuss in a separete posting

 

 
Date: Friday Sep 30, 2011 3:52:35 PM (Arbitration Response Id: 1,677,299)
From: Tim Yates (vWorker) (Arbitrator)
To: scottie05 (employer),MOTASH  (worker)
 

Motash,

You wrote:

A-There's a bug/incompatability with latest MSN, that makes its setup on my PC not possible for the moment,to explain :
while trying to replicate the crash problem, that is claimed by employer,i removed my version, and gave trials, but failed to get a version 14x installation, and from since i'm not able to setup latest MSN again(the setup logs attached proofs setup errors from 6-9-2011),

You have known about this error since September 6th, but did not contact Microsoft for support until September 28th?

Diane,

I see that you have set a deadline, however, this deadline is not valid as the project is still in arbitration.

Motash has proposed a deadline. Is that acceptable? Do you want to wait?
 

Regards.
Tim Yates (vWorker)



P.S. Automated warning about upcoming deadline(s). Employer must respond before Wednesday Oct 5, 2011 3:52:35 PM EDT. Worker must respond before Wednesday Oct 5, 2011 3:52:35 PM EDT. If you can respond sooner, please do so, as it will speed up the arbitration process for both parties. Thanks.
 

 
Date: Friday Sep 30, 2011 4:47:24 PM (Arbitration Response Id: 1,677,320)
From: scottie05 (employer)
To: Tim Yates (vWorker)  (arbitrator)
CC: MOTASH  (worker)
 


Now I am clear that arbitration is not yet over, I understand that the deadline I set does not apply.  I don't accept that an implied deadline remains in place, of course, because I was not the instigator of this arbitration and it has prevented me from correcting that situation.



Apologies for the long-winded answer; I can't determine from his message what that deadline is, if you can interpret for me then pehaps I can answer differently.



It seems to me that MOTASH is proposing an indefinite deadline, based on when he receives a fix from Microsoft.



I have a critical memory leak posted to the same set of forums that has been open and unresolved for 6 weeks with no resolution in sight.   The MS forums don't guarantee a fix or even a response, particularly as this appears to be problem of configuration on his PC, although of course I don't claim to know that is a fact.



Given that I had a hard deadline of today for delivery of phase 2, while this only phase 1, I have basically lost the opportunity to achieve anything useful with this code (and a great deal of credibility with my client), for no reason, it seems.  



It does not seem possible to get a single, straightforward answer from this developer that I can understand. I hope I'm not doing the same here.  The short answer is no.  If Motash is proposing that I wait indefintiely while he resolves his tech support issue, that is not something I can agree to.



 



 



 



 



 



 



 



 



 


 

 
Date: Saturday Oct 1, 2011 7:57:31 PM (Arbitration Response Id: 1,677,693)
From: MOTASH (worker)
To: Tim Yates (vWorker)  (arbitrator)
CC: scottie05 (employer)
 
Tim,

you asked :
You have known about this error since September 6th, but did not contact Microsoft for support until September 28th?

My Answer:

Yes because :
1-Usually before i claim that a problem is not caused by my configuration i have to do checks,trials(re-download,check complete uninstall,..),as you can see in the logs 8 setup trials in the period 6-9/9/2011, till i gave up
2-i believe (and i still do) that the employer had made faults and broke the contract,unless for your decision (which i will keep any right to discuss/dispute/get in public after a full review to my whole arbitration experience),resuming of project was not probable
3-by terms,during arbitration i'll not have the chance to provide new code, so as being busy, there seems no need to solve a unlogic problem (bad connection and actually it's good)
4- when the deadline issue was raised by the end of the month, i did give more trials on 26-28/9/2011 to be ready for all possibilities
5-finally for my self i wouldn't actually contact microsoft,as i mentioned i was trying to get a formal reply, but rather wait for a stable version to be released, so that was my personal attitude as i was not obliged to address any project development during arbitration


 

 
Date: Sunday Oct 2, 2011 10:12:16 PM (Arbitration Response Id: 1,677,885)
From: MOTASH (worker)
To: Tim Yates (vWorker)  (arbitrator)
CC: scottie05 (employer)
 
Tim,

Since the final decision is to resume project,I've an idea to resolve the deadline issue, after all an escrow in my favor has been delayed too long

i've a final code version(i pointed to,in my posts with employer),and due to lacking trust towards the employer,if you may test the executables(as a neutral environment, and may the employer too, but your feedback is what matters to me) and find it OK, then we would have passed the deadline issue and the whole arbitration (Procedurally)

i might have attached it already, but i don't know if the idea is acceptable, and doesn't violate arbitration rules

Kindly Advice.
 

 
Date: Monday Oct 3, 2011 11:29:15 AM (Arbitration Response Id: 1,678,156)
From: Tim Yates (vWorker) (Arbitrator)
To: scottie05 (employer),MOTASH  (worker)
 

Motash,

If you are stating that the work is complete, then please upload the files. The way testing works is that the employer would have the option of testing them first and confirming if they work or not. If they believe that there are errors remaining, they could fill out a flaw list and then vWorker would complete the testing.

If you do not believe work to be complete, then I will impose a ruling on the deadline.


Regards.
Tim Yates (vWorker)



P.S. Automated warning about upcoming deadline(s). Worker must respond before Thursday Oct 6, 2011 11:29:15 AM EDT. If you can respond sooner, please do so, as it will speed up the arbitration process for both parties. Thanks.
 

 
Date: Monday Oct 3, 2011 5:46:19 PM (Arbitration Response Id: 1,678,543)
From: MOTASH (worker)
To: Tim Yates (vWorker)  (arbitrator)
CC: scottie05 (employer)
 
Tim,

the chances are equal,that my code will work for the new version,or may not
So, i'd better stick to my proposed deadline

Since, Completion will be the next step, a completion criteria should be stated, as i believe it will be the next arbitration title, for the following reasons:
1- the employer made me work after the deadline to address his version of MSN (Employer Posting # 36,581,108 on Tuesday Aug 23, 2011 11:55:56 AM), which is now clear that it was not part of the contract(work period 23 Aug-6Sep)
2-the employer did tests,claimed a fault in my code and tried to commit me to platform(64bit)that we agreed earlier it will not be part of the contract
3-the employer claimed the same fault on agreed 32bit platform, and couldn't prove it

for these reasons i request the project completion criteria to be well stated
and i'll start by quoting the employer words on the same posting 36,581,108 :
"If we can correct this issue, the remainder can be considered maintenance and I can call this complete"

 

 
Date: Tuesday Oct 4, 2011 3:05:58 PM (Arbitration Response Id: 1,679,160)
From: Tim Yates (vWorker) (Arbitrator)
To: scottie05 (employer),MOTASH  (worker)
 

Motash,

You will not be able to hold up the project indefinitely to get the issue regarding MSN fixed. You are responsible for your working environment.

You have one day to get the MSN issue resolved and then 2 days to deliver the remaining work (for a total of 3 business days).

The target OS are: Target OS is  Vista SP1, Windows 7 32 bit only. XP is excluded as it is not supported by the latest MSN.

The target MSN Live is the latest available.
 

If you have questions regarding the deliverables, please state them now, otherwise work may begin.

Regards.
Tim Yates (vWorker)

 

 
Date: Tuesday Oct 4, 2011 4:10:42 PM (Arbitration Response Id: 1,679,201)
From: MOTASH (worker)
To: Tim Yates (vWorker)  (arbitrator)
CC: scottie05 (employer)
 
Tim,

the worker contract states :
"c) Setup program bug items (applies to software-related projects only):

The flaw list may contain reference to items caused by a faulty setup program. Due to the exponential number of different computer configurations in the world, setup programs sometimes do not run perfectly on every machine. More importantly, sometimes these issues cannot be identified until they are run on a particular "problem configuration" machine. If the tester determines that one or more setup program related flaw items fall in this category and could not have been prevented by the Worker using adequate testing using their own equipment and proper testing measures commensurate with the project, then these flaw items will not be considered "

and you say "You are responsible for your working environment"


Committing to the deadline you impose, doesn't mean that i accept it, nor forfeits any right given to me to argue/dispute it in any time, but only because i'm not going to loose that escrow that i deserve
and kindly when the project to be resumed, in advance give me a specific date:time to start counting 72hours

- correction : Target OS is "(Vista SP1, Windows 7)" 32 bit only
- "The target MSN Live is the [latest] available" , is unspecific, what if a newer version is released within 3 days, to my knowledge MSN v15.4.3538.0513 is the latest at the moment,and it will be the version that may be subject to any further tests
- You ignored my question about contract terms, that will rule and by which i can send a work completion

Finally inform me, about the questions that should raise regarding deliverables
 

 
Date: Wednesday Oct 5, 2011 2:39:55 PM (Arbitration Response Id: 1,679,863)
From: Tim Yates (vWorker) (Arbitrator)
To: scottie05 (employer),MOTASH  (worker)
 
Note: 1 long word(s)/URL(s) in this posting > 65 characters was/were broken up with spaces to prevent it/them from stretching the screen and making it difficult to read.

Motash,

You wrote:

the worker contract states :
"c) Setup program bug items (applies to software-related projects only):

The flaw list may contain reference to items caused by a faulty setup program. Due to the exponential number of different computer configurations in the world, setup programs sometimes do not run perfectly on every machine. More importantly, sometimes these issues cannot be identified until they are run on a particular "problem configuration" machine. If the tester determines that one or more setup program related flaw items fall in this category and could not have been prevented by the Worker using adequate testing using their own equipment and proper testing measures commensurate with the project, then these flaw items will not be considered "

and you say "You are responsible for your working environment"


This portion of the worker's contract that you are quoting is regarding flaws on the flaw list, which we are not using becasue the work is not compete. It also refers to a setup program, which is also not applicable in this case.

Committing to the deadline you impose, doesn't mean that i accept it, nor forfeits any right given to me to argue/dispute it in any time, but only because i'm not going to loose that escrow that i deserve
and kindly when the project to be resumed, in advance give me a specific date:time to start counting 72hours


Because both the employer and worker could not agree on a deadline, it is up the arbitrator to impose a deadline. If you wish to pull out of the project you will receive a rating of 3 and you will be responsible for the cancellation fee. Please confirm that you understand this and I will close out the arbitration. Otherwise, work will continue.

You may begin work as soon as the deadline is set.

- correction : Target OS is "(Vista SP1, Windows 7)" 32 bit only
- "The target MSN Live is the [latest] available" , is unspecific, what if a newer version is released within 3 days, to my knowledge MSN v15.4.3538.0513 is the latest at the moment,and it will be the version that may be subject to any further tests


You may use the latest MSN version that is available when you begin work.

- You ignored my question about contract terms, that will rule and by which i can send a work completion

I do not see a question in your previous post. Again, you were asked previously regarding your posting to be specific. If you have questions regarding the work to be completed - Diane gave an explantion for what needs to be completed in Arbitration Response Id: 1,672,263. You were also asked in Arbitration Response Id: 1,674,916, regarding what additional work was requested that you believed was not part of the contract. Your reponse did not list any additional work.

Finally inform me, about the questions that should raise regarding deliverables

I do not know what you mean by this statement. Your deliverables would have to meet the project summary.

Diane,

Please now set the new deadline via the site to make it legal/official, and also to prevent the automated email reminders from being sent to you to update it. To do this, go to the project URL at: http://www.vWorker.com/RentACoder/misc/BidRequests/ShowBidReque st.asp?lngBidRequestId=1707024. At the top (under the title), there is a link that says, "My employer project panel".  Click the link, then click on "Extend delivery deadline", and follow the prompts. You'll notice that the project page now reflects your new deadline.

Please let me know when you've done this so we can continue. If you have any questions about this, please let me know.



Regards.
Tim Yates (vWorker)

P.S. Automated warning about upcoming deadline(s). Employer must respond before Monday Oct 10, 2011 2:39:55 PM EDT. Worker must respond before Monday Oct 10, 2011 2:39:55 PM EDT. If you can respond sooner, please do so, as it will speed up the arbitration process for both parties. Thanks.
 

 
Date: Wednesday Oct 5, 2011 5:38:29 PM (Arbitration Response Id: 1,679,954)
From: scottie05 (employer)
To: MOTASH  (worker),Tim Yates (vWorker)  (arbitrator)
 
As the worker would not agree to extend the delivery deadline, and the arbitrator did not impose one, I have imposed my own: 24 hours.

I have done this because the vworker insists that I follow the rules or forfeit arbitration. 

I still maintain that the developer marking the project finished overrules any implied deadline.




 

 
Date: Wednesday Oct 5, 2011 9:43:16 PM (Arbitration Response Id: 1,680,013)
From: MOTASH (worker)
To: Tim Yates (vWorker)  (arbitrator)
CC: scottie05 (employer)
 
Tim,

as per my contract your judgment word as an arbitrator is final, so as i've done before,discussing the reasoning of your judgment will delay the process, so i'll stress only on points that keep pushing forward


A - My question about test criteria:
first,as we were ordered not to respond to other parties arbit. posting,then our postings do NOT commit the other party as they are not discussed mutually
My point here: i continued working after deadline 1-the employer fully accepted my work except for on issue(the claimed crash in my code)
2-the employer accepted to put any other incompatibility with the original contract terms to be done later as maintenance
** Reference : Employer Posting # 36,581,108
So,to avoid any coming Work Completion arbitration that may be raised by the employer, i requested this to be judged and cleared here, as it's subject to the address of this arbitration(contract terms disagreements)

B-MSN Version:
Again the word LATEST is specific at a given moment, but since we are talking about a deadline (time span),a given version must be clear to rule from project resumption till deadline

C-Deliverables Questions:
you wrote "If you have questions regarding the deliverables, please state them now"
i did not understand your request, so i asked you to inform me about possible questions that may raise towards deliverables

D-Finally, Deadline :
I confirm that i understand your authority to impose the deadline, and i already had stated that i commit to it
the employer set a 24hrs deadline,and it's your fault that you addressed me alone with the value of the deadline
So please advice,i will not start because the given deadline is not what i was informed(72hrs)
 

 
Date: Thursday Oct 6, 2011 3:47:37 PM (Arbitration Response Id: 1,680,646)
From: Tim Yates (vWorker) (Arbitrator)
To: scottie05 (employer),MOTASH  (worker)
 
Diane,

You wrote:

As the worker would not agree to extend the delivery deadline, and the arbitrator did not impose one, I have imposed my own: 24 hours.

I imposed a deadline in Arbitration Response Id: 1,679,160


You have one day to get the MSN issue resolved and then 2 days to deliver the remaining work (for a total of 3 business days).

Please set the deadline for 3 business days. Please post back to the arbitration to let Motash know that the new deadline is set so that he can begin.

I have done this because the vworker insists that I follow the rules or forfeit arbitration.

I still maintain that the developer marking the project finished overrules any implied deadline.


Motash has not claimed that he is 100% complete and was given several opportunities to do so. The response in Posting # 36,728,332 on Monday Sep 5, 2011 11:06:33 AM, 
 cannot be regarded as a statement that he is 100% complete.


Motash,

You wrote:

A - My question about test criteria:
first,as we were ordered not to respond to other parties arbit. posting,then our postings do NOT commit the other party as they are not discussed mutually
My point here: i continued working after deadline 1-the employer fully accepted my work except for on issue(the claimed crash in my code)
2-the employer accepted to put any other incompatibility with the original contract terms to be done later as maintenance
** Reference : Employer Posting # 36,581,108
So,to avoid any coming Work Completion arbitration that may be raised by the employer, i requested this to be judged and cleared here, as it's subject to the address of this arbitration(contract terms disagreements)


The work that you complete must meet the contract. If you fix one issue, but break another part of the deliverables, you would still be responsible for meeting the contract.

B-MSN Version:
Again the word LATEST is specific at a given moment, but since we are talking about a deadline (time span),a given version must be clear to rule from project resumption till deadline


When I went to Microsoft's website - the file version on the latest download was 15.4.3538.513. Use that one.

C-Deliverables Questions:
you wrote "If you have questions regarding the deliverables, please state them now"
i did not understand your request, so i asked you to inform me about possible questions that may raise towards deliverables


If you have questions regarding the project, you may address them to the employer.

D-Finally, Deadline :
I confirm that i understand your authority to impose the deadline, and i already had stated that i commit to it
the employer set a 24hrs deadline,and it's your fault that you addressed me alone with the value of the deadline
So please advice,i will not start because the given deadline is not what i was informed(72hrs)


The deadline starts when Diane sets the new deadline. She has permission to set the new deadline.

Regards.
Tim Yates (vWorker)

P.S. Automated warning about upcoming deadline(s). Employer must respond before Tuesday Oct 11, 2011 3:47:37 PM EDT. If you can respond sooner, please do so, as it will speed up the arbitration process for both parties. Thanks.
 

 
Date: Friday Oct 7, 2011 10:20:33 AM (Arbitration Response Id: 1,680,911)
From: MOTASH (worker)
To: Tim Yates (vWorker)  (arbitrator)
CC: scottie05 (employer)
 
Tim,

Points B,C,D are clear
** about the deadline,i confirm it's 3 BUSINESS days as you imposed, not 72hrs as i mentioned earlier

While for Point A:
to avoid general answers,i'll try to be more specific in my question:
on posting 36,581,108 the employer said
"If we can correct this issue, the remainder can be considered maintenance and I can call this complete"

My Question :
if the project came to "Not Complete Arbitration",Can the employer state Flaw List items, that he already accepted in the above mentioned posting?

 

 
Date: Friday Oct 7, 2011 11:55:51 AM (Arbitration Response Id: 1,681,005)
From: scottie05 (employer)
To: MOTASH  (worker),Tim Yates (vWorker)  (arbitrator)
 
Tim,

You wrote:
The response in Posting # 36,728,332 on Monday Sep 5, 2011 11:06:33 AM, cannot be regarded as a statement that he is 100% complete.

However, Posting # 36,700,667 on Friday Sep 2, 2011 2:01:21 PM can and was.  No instructions I can find in vWorker agreements say that any communication after a worker reports a project complete that further communications or defect lists impose an implied deadline on the project or expose the employer to this level of risk. If I have missed something, please send me a link.

The only deadlines I have imposed since that posting have been since are in reponse to arbitration and do not apply.

Btw, I do not agree to three business days.  If the arbitrator wishes to impose such a deadline, it is possible that is within the rules, but the arbitrator may not instruct me to impose such a deadline.   Please let the record show that the arbitrator, not the employer, changed the deadline on the project.

We did not initiate this unwarranted arbitration, nor do any of the vWorker agreements indicate that an arbitration could extend for 30 days or more while transgressions to the arbitration -- including but not limited to unwarranted and unsubstantiated accusations-- would be ignored, when it is reasonable to assume they would result in a quicker solution.

If myself or my organization were at fault, we would perhaps be more flexible.  No such fault has been proven. 

Even if vWorker arbitration rules are so inflexible that vworker can do anything they wish under any circumstances, we still would not accept this is a reasonable outcome or one that should be permitted to damage my organization futher -- not without the strongest possible measures being taken to ensure it does not happen to anyone else.

Thank you.

 
 

 
Date: Tuesday Oct 11, 2011 2:49:37 PM (Arbitration Response Id: 1,682,786)
From: Tim Yates (vWorker) (Arbitrator)
To: scottie05 (employer),MOTASH  (worker)
 
Note: 1 long word(s)/URL(s) in this posting > 65 characters was/were broken up with spaces to prevent it/them from stretching the screen and making it difficult to read.

Motash,

You wrote:

if the project came to "Not Complete Arbitration",Can the employer state Flaw List items, that he already accepted in the above mentioned posting?

I've not looked into this issue because we are not in final testing, but that statement would seem to indicate that this would possibly be acceptable. However, if new bugs were introduced that did not fall under the previous posting, then these would need to be addressed.

Diane,

You wrote:

However, Posting # 36,700,667 on Friday Sep 2, 2011 2:01:21 PM can and was. No instructions I can find in vWorker agreements say that any communication after a worker reports a project complete that further communications or defect lists impose an implied deadline on the project or expose the employer to this level of risk. If I have missed something, please send me a link.

In Alert # 4,395,285 on Wednesday Aug 31, 2011 2:01:18 PM, you are told:

However, if MOTASH is not able to complete your project 100% by the above deadline, then you have 2 choices. You can either continue working with them or cancel the project (and request a refund of unescrowed funds). However it is VERY IMPORTANT that you read this email to learn how to do this properly. Doing so incorrectly may cost you UNNECESSARY TIME and cause you UNDUE FRUSTRATION.

Please read the entire alert.

Btw, I do not agree to three business days. If the arbitrator wishes to impose such a deadline, it is possible that is within the rules, but the arbitrator may not instruct me to impose such a deadline. Please let the record show that the arbitrator, not the employer, changed the deadline on the project.

I have imposed the deadline as both of you could not agree on a deadline. This was explained in Arbitration Response Id: 1,679,863 and Arbitration Response Id: 1,680,646.  Because you have not set the deadline, Motash does not have to begin the work and you are delaying the completion of the work.

If you do not wish to set a deadline, you may pull out of the project and you will receive a rating of 3 and Motash will be paid for the work he has done up to this point. Please let me know if you wish to pull out at this time. Otherwise, please set the deadline on the site, following the instructions you received previously. Failure to do so will result in forfeiture.

If myself or my organization were at fault, we would perhaps be more flexible. No such fault has been proven.

Even if vWorker arbitration rules are so inflexible that vworker can do anything they wish under any circumstances, we still would not accept this is a reasonable outcome or one that should be permitted to damage my organization futher -- not without the strongest possible measures being taken to ensure it does not happen to anyone else.


When the worker misses a deadline, you can either cancel and receive a refund if the project is not 100% complete, or choose to continue to work with them. If you choose to work with them, that is fine...but it is vitally important that you set a new deadline. You were warned in the email notification you received when the project became overdue, that if you continued work but didn't set a new deadline, you would be doing a dangerous thing and would be working without the protection of a deadline. (The reason for this rule, called the “implicit extension” rule, is to protect workers from unscrupulous employers who could use the loophole to get a worker to do all sorts free work, and then retroactively 'cancel' for a deadline missed weeks or months earlier.) If you didn't get a chance to read that email, I recommend that you do so now: http://www.vWorker.com/RentACoder/SoftwareBuyers/Articles/RacEm ails/BuyerNotificationOfDeadlineComing.asp.

Had you actually set a deadline, you would now been in an extremely strong position. A project where the deadline has expired is either 100% complete or isn't. If it isn't 100% complete, then you would receive a full refund. We simply test the project and determine if it's 100% complete or not and then refund your funds. This gives you maximum protection.

However, since you didn't set a new deadline, we can't fairly test for the project being 100% complete on time, when there is no agreement between the two of you as to when the project should be 100% complete. So now if you unilaterally pullout, you would be the one breaking the contract instead of the worker. You would have to pay the worker for the time invested (a partial payment). Additionally a rating notating that you pulled out would have to be put on your record. (Again, if it weren't this way, an unscrupulous employer could use that loophole to get free work out of workers…as described above).


Regards.
Tim Yates (vWorker)

P.S. Automated warning about upcoming deadline(s). Employer must respond before Friday Oct 14, 2011 2:49:37 PM EDT. If you can respond sooner, please do so, as it will speed up the arbitration process for both parties. Thanks.
 

 
Date: Tuesday Oct 11, 2011 3:34:19 PM (Arbitration Response Id: 1,682,833)
From: MOTASH (worker)
To: Tim Yates (vWorker)  (arbitrator)
CC: scottie05 (employer)
 
Tim,    

I'm having  a Yes and No Reply, and what I don't understand how you distinguish between what you call New Bugs , and what the employer calls the remainder can be considered maintenance , i believe the employer statment is clear that i have one issue left and nothing else i should address

what i conclude from your reply that:  this is a delicate issue with deep details, that should be considered when 100% Completion is addressed
On the other hand, if the employer kept delaying the progress, it's better if i could make use of this time, by asking you to address this issue with its details, and Kindly give me a more specific reply
 

 
Date: Tuesday Oct 11, 2011 4:00:06 PM (Arbitration Response Id: 1,682,853)
From: scottie05 (employer)
To: MOTASH  (worker),Tim Yates (vWorker)  (arbitrator)
 
Tim:

You said:

"When the worker misses a deadline, you can either cancel and receive a refund if the project is not 100% complete, or choose to continue to work with them."

This has nothing to do with the
worker marking the project finished.

I am setting the deadline to 3 days, simply because you will unilaterally confiscate these funds if I don't. 



 

 
Date: Wednesday Oct 12, 2011 9:44:55 AM (Arbitration Response Id: 1,683,189)
From: scottie05 (employer)
To: MOTASH  (worker),Tim Yates (vWorker)  (arbitrator)
 
Please let me know when the arbitration is over.  I cannot interact with the project until arbitration has been marked complete.
 

 
Date: Wednesday Oct 12, 2011 10:42:37 AM (Arbitration Response Id: 1,683,297)
From: MOTASH (worker)
To: scottie05 (employer)
CC: Tim Yates (vWorker)  (arbitrator)
 
Attn Employer :

you had already sent me postings and deadlines before, while the arbitration was not yet completed
i got a notification from you with a new deadline, that follows the agreement here(imposed by arbitrator)
So project resumption is confirmed by action of yours not mine

So i was clear that your fastest response is required, no need to remind you that you committed yourself to 24Hrs reply time
i'm working in good faith and already sent you the executables to test, hopefully you don't break our contract


Attn Tim:

Kindly be noted, that i'm working faithfully to my contracts with employer, vworker and the results of this arbitration(wether i like it or not)

* this arbitration was started because the employer tried to commit me to an older version of MSN for the period(23-8 to 6-9 ), upon which i started this arbitration which ruled in my favour to use the latest MSN Version

* the employer used unagreed platforms in tests, also claimed faults on agreed platforms that he couldn't proof

* also he stated incorrect statments in arbitration i didn't have the chance to answer( just for ex: refer to posting 36,643,166 on 28 Aug where he states that the problem is new and he had earlier versions working ), upon which you stated that he's not at fault

* the employer tried to force me to unagreed deadlines, while the project was in explicit state

* the employer stalled project resumption for no reason

* finally the employer is trying to escape from his committments with me of 24hrs feedback time

* with all the above mentioned points,the employer trials to commit me to unagreed version and putting the project into explicit state, were accompanied with promises of future work ( posting 36,524,174 on 18 Aug , 36,556,198 on 21 Aug )that gives an impression of unscrupulous behaviour


Pease advice
 

 
Date: Wednesday Oct 12, 2011 11:49:46 AM (Arbitration Response Id: 1,683,366)
From: Tim Yates (vWorker) (Arbitrator)
To: scottie05 (employer),MOTASH  (worker)
 
Diane,

You wrote:

This has nothing to do with the worker marking the project finished.

I assume you are referring to Posting # 36,700,667 on Friday Sep 2, 2011. This is not an admission by the worker that the work is 100% complete. This statement is generated by the vworker website. You continued to work with Motash after the deadline expired and did not set a new one.

Please let me know when the arbitration is over. I cannot interact with the project until arbitration has been marked complete.

Motash has updated the deliverables. It is your job to test them. If you do not test them or test them and do not give Motash enough time to fix any issues would mean that you would most likely be at fault if there were any issues. Please test the work and report any issues, or release the funds if they meet the project summary.

Motash,

You wrote:

the employer stalled project resumption for no reason

* finally the employer is trying to escape from his committments with me of 24hrs feedback time




I never asked Diane to give me their opinion of you. Similarly, I did not ask you to give me your opinion of Diane.

Arbitration is based on facts…not opinions. As an example: if I should ask you if Diane has been communicating completely onsite, I am asking you for facts in return. So you should respond with “yes” or “no” and provide details related to the facts (if pertinent). You should NOT tell me that you think (as an example) that Diane is a cheat, incompetent, a deliberate liar, etc. That is the difference between facts (which are knowable) and opinions (which are either subjective or your guesses as to what Diane is thinking). Please do not post any more opinions about the other party.

Further, Mohamed, opinion posting is unprofessional and insulting to the other party, and both parties are entitled to be free of such behavior in arbitration. So if you do post an opinion again, I will be forfeiting you. I would rather arbitrate based on the facts at hand rather than a premature forfeiture, so I hope you will cooperate and avoid this by not posting any more opinions.

Regards.
Tim Yates (vWorker)
 

 
Date: Wednesday Oct 12, 2011 3:07:29 PM (Arbitration Response Id: 1,683,555)
From: scottie05 (employer)
To: Tim Yates (vWorker)  (arbitrator)
CC: MOTASH  (worker)
 
The program fails all tests on Windows 7.

So that the developer does not have grounds for any more libellous accusations, nor the arbitrator further suggest we might somehow be stalling/retaliating, we are documenting these fully.  This will take some time, but we will upload as soon as that is complete.

We do not believe this developer is competent to complete the work as specified.

We do not believe sufficient progress has been made.

Were this not in arbitration, we would place it into arbitration.  This option is denied to us.  
 

 
Date: Wednesday Oct 12, 2011 3:28:37 PM (Arbitration Response Id: 1,683,565)
From: scottie05 (employer)
To: Tim Yates (vWorker)  (arbitrator)
CC: MOTASH  (worker)
 
Tim:

Will this project remain in arbitration until closed? 

If so, how would I be able to raise an arbitration of my own if it became necessary?

Am I no longer protected, simply because the worker decided to arbitrate instead of addressing the defect list I reported at that time?


 

 
Date: Wednesday Oct 12, 2011 3:37:04 PM (Arbitration Response Id: 1,683,571)
From: scottie05 (employer)
To: MOTASH  (worker)
CC: MOTASH  (worker)
 
Attached File
1.16 MB

Please find attached the defect list and supporting evidence.

The product is less functional each time it is tested.

The defects are such that it is impossible to completely test all requirements ("blocker" issues).

We have not agreed to an indefinite test/fix cycle and do not have the resources for more than one more round of testing.

Please advise next steps.

 

 
Date: Thursday Oct 13, 2011 1:15:23 AM (Arbitration Response Id: 1,683,666)
From: MOTASH (worker)
To: Tim Yates (vWorker)  (arbitrator)
CC: scottie05 (employer)
 
Tim,

you wrote "Arbitration is based on facts…not opinions" also "provide details related to the facts", while when i provide details and references you reply me "Please keep your responses short"

As i'm seeking to be professional and avoid such mistake(if exists) in the future, i'm asking for your help to point me which of these points is opinion based, upon which i'll be glad to apologize for such behavior:-


1-"this arbitration was started because the employer tried to commit me to an older version of MSN for the period(23-8 to 6-9 ), upon which i started this arbitration which ruled in my favour to use the latest MSN Version"
Proofs :-
A-employer posting 36,581,108 23-Aug "The crash in my version of MSN Live/ Messenger is a concern"
B- arbit. resp. 1,671,372 20-9 "the latest version would be used"


2-"the employer used unagreed platforms in tests, also claimed faults on agreed platforms that he couldn't proof"
Proofs :
A- employer posting 36,704,39 2-9 "The last set of tests was on a 64bit" , "but it happens on all OSes"
B- attachment on 36,704,482 2-9 doesn't contain the claimed fault "[SEH] HookDLLApi" on 32bit


3-"also he stated incorrect statments in arbitration i didn't have the chance to answer, upon which you stated that he's not at fault"
Proofs :-
A- employer posting 36,643,166 28-8 "I have been testing all along on MSN live, so it must be a relatively recent change that caused the problem"
B- as instructed i can't address the specific arbit. response, but as a fact he claimed never had my program working with MSN


4-"the employer tried to force me to unagreed deadlines, while the project was in explicit state"
Proofs:-
A- Alert 4,441,169 on 27-9
B- Alert 4,454,116 on 5-10


5-"the employer stalled project resumption for no reason"
Proofs:-
A- arbit resp 1,680,646 on 6-10 "set the deadline for 3 business days"
B- again as instructed not to address employer response, but as a fact he refused to put a deadline by himself
C-finally the deadline is set by Alert 4,463,936 on 11-10 ( 6days late from 6-10)


6-"finally the employer is trying to escape from his committments with me of 24hrs feedback time"
Proofs:-
A- Posting 36,323,905 on 2-8 "Any delays from my end >24hs will result in me changing the deadline accordingly"
B- arbit resp 1,683,189 on 12-10 "I cannot interact with the project until arbitration has been marked complete"


7-"with all the above mentioned points,the employer trials to commit me to unagreed version and putting the project into explicit state, were accompanied with promises of future work, that gives an impression of unscrupulous behaviour"
Proofs:-
A- all above points/proofs
B- posting 36,464,432 on 13-8 -> long paragraph
C- posting 36,524,174 on 18-8 "I do have a question regarding the next project , ...."
D- posting 36,556,198 on 21-8 -> long paragraph
E- as a fact i did a free work, confirmed by posting 36,464,432 on 13-8 "I may be able to arrange a bonus to make up the difference" , posting 36,556,198 on 21-8 "I will see what I can do about making up the difference"


kindly tim, as a senior arbitrator, and me as a few month old freelancer, tell me which of the 7 points is opinion and which is a fact


By the way, the employer is sending me private responses on this page (Arbitration Response Id: 1,683,571) is that allowed ?

I'm seeking guidance as this conversation will by no way delay the progress of project,as the clock is already ticking tworads the deadline
Your help will be much appreciated
Thanks in advance,
MOTASH
 

 
Date: Thursday Oct 13, 2011 11:55:01 AM (Arbitration Response Id: 1,683,960)
From: scottie05 (employer)
To: Tim Yates (vWorker)  (arbitrator)
CC: MOTASH  (worker)
 

Tim:

For the record, I have not sent the worker any private responses since being advised not to be the original arbitrator.    The checkboxes do not always check correctly, and it should be obvious that a repeated TO and CC is a mistake.

Such an accusation is another falsehood, and I suspect the arbitrator will continue to ignore violations to the arbitration agreement.    The belated warning to the worker was long past the point of insult. 

I have also requested clear direction from you guidance on when/how the arbitration process ends.  I would have thought either when the ruling was made or when the final delivery date was imposed, but neither of those appear to be the case.
 

 
Date: Thursday Oct 13, 2011 1:26:40 PM (Arbitration Response Id: 1,684,033)
From: Tim Yates (vWorker) (Arbitrator)
To: scottie05 (employer),MOTASH  (worker)
 
Motash,

In Arbitration Response Id: 1,683,366, I specifically quoted the two responses which were opinions. If you have concerns in the future regarding whether your statements will be seen as opinions, I would recommend not writing them. You are not allowed to post opinions about the other person, even if you believe them to be fact. Please use this as your guide.


By the way, the employer is sending me private responses on this page (Arbitration Response Id: 1,683,571) is that allowed ?

That response was not private.

Diane,

You wrote:

I have also requested clear direction from you guidance on when/how the arbitration process ends. I would have thought either when the ruling was made or when the final delivery date was imposed, but neither of those appear to be the case.


The deadline is tomorrow. It is your responsibility to test any work that Motash has delivered as I explained in Arbitration Response Id: 1,683,366. If the project does not meet your expectations, you are required to let Motash know in a reasonable time in order for them to make corrections. It appears that you have done this in Arbitration Response Id: 1,683,571.  However, I have not looked at this document.

Once the deadline has past, if the work does not meet your expectations, it can then go for 100% testing. You will be able to fill out a flaw list and Motash would be able to respond to it. I would then test the work. For more information on the process, you can view the description at the Employer's Contract, which is available in a link below on the arbitration page. You could raise an insufficient progress arbitration at this time, however, I would not recommend it as:

1. The deadline is fast approaching.
2. It can be difficult to prove that they could not fix the issues by the deadline.

If you have any other questions regarding the process, please let me know.

Regards.
Tim Yates (vWorker)
 

 
Date: Thursday Oct 13, 2011 3:00:28 PM (Arbitration Response Id: 1,684,134)
From: scottie05 (employer)
To: Tim Yates (vWorker)  (arbitrator)
CC: MOTASH  (worker)
 
Tim:

That's certainly not what was explained, and it is not in the employer agreement. I just checked.

I had already stated that I do not have the bandwidth for this number of tests, particularly as this unnecessary arbitration has cost me the original contract, so the code is useless.

Because vworker has not followed its own arbitration rules (so called opinions above are not opinions, and meet the legal definition of libel) and has unnecessarily delayed arbitration:

I am deliberately forfeiting this aribtration. 

This arbitration has not been remotely fair or impartial whatever you and your policies claim.  You have repeatedly ignored transgressions by the worker and forced my actions based on one technicality while ignoring others at your convenience.

If you wish to release those funds to this incompetent, untruthful, insulting, and combative worker, and refuse to warn others what could happen to them if they pick him, it seems I am unable to prevent you, but I will not add insult to injury by testing his horribly unstable and inadequate code in my test lab any longer.

I will be filing complaints against vworker, and then I will be moving on.

Please ensure my account is closed with immediate effect.  I will not under any circumstances use your poorly arbitrated high-risk service any longer.

 

 
Date: Thursday Oct 13, 2011 3:10:01 PM (Arbitration Response Id: 1,684,148)
From: vWorker Agent (vWorker ) (Arbitrator)
To: scottie05 (employer),MOTASH  (worker),Tim Yates (vWorker)  (arbitrator)
 
Automated alert: vWorker.com noticed that scottie05 closed their account. Notifying arbitrator...
 

 
Date: Thursday Oct 13, 2011 3:10:01 PM (Arbitration Response Id: 1,684,149)
From: vWorker Agent (vWorker ) (Arbitrator)
To: scottie05 (employer),MOTASH  (worker),Tim Yates (vWorker)  (arbitrator)
 
Automated alert: vWorker.com noticed that scottie05 closed their account. Notifying arbitrator...
 

 
Date: Thursday Oct 13, 2011 3:10:02 PM (Arbitration Response Id: 1,684,150)
From: vWorker Agent (vWorker ) (Arbitrator)
To: scottie05 (employer),MOTASH  (worker),Tim Yates (vWorker)  (arbitrator)
 
Automated alert: vWorker.com noticed that scottie05 closed their account. Notifying arbitrator...
 

 
Date: Thursday Oct 13, 2011 3:10:02 PM (Arbitration Response Id: 1,684,151)
From: vWorker Agent (vWorker ) (Arbitrator)
To: scottie05 (employer),MOTASH  (worker),Tim Yates (vWorker)  (arbitrator)
 
Automated alert: vWorker.com noticed that scottie05 closed their account. Notifying arbitrator...
 

 
Date: Thursday Oct 13, 2011 3:10:02 PM (Arbitration Response Id: 1,684,152)
From: vWorker Agent (vWorker ) (Arbitrator)
To: scottie05 (employer),MOTASH  (worker),Tim Yates (vWorker)  (arbitrator)
 
Automated alert: vWorker.com noticed that scottie05 closed their account. Notifying arbitrator...
 

 
Date: Thursday Oct 13, 2011 3:10:03 PM (Arbitration Response Id: 1,684,153)
From: vWorker Agent (vWorker ) (Arbitrator)
To: scottie05 (employer),MOTASH  (worker),Tim Yates (vWorker)  (arbitrator)
 
Automated alert: vWorker.com noticed that scottie05 closed their account. Notifying arbitrator...
 

 
Date: Thursday Oct 13, 2011 3:10:03 PM (Arbitration Response Id: 1,684,154)
From: vWorker Agent (vWorker ) (Arbitrator)
To: scottie05 (employer),MOTASH  (worker),Tim Yates (vWorker)  (arbitrator)
 
Automated alert: vWorker.com noticed that scottie05 closed their account. Notifying arbitrator...
 

 
Date: Thursday Oct 13, 2011 3:10:03 PM (Arbitration Response Id: 1,684,155)
From: vWorker Agent (vWorker ) (Arbitrator)
To: scottie05 (employer),MOTASH  (worker),Tim Yates (vWorker)  (arbitrator)
 
Automated alert: vWorker.com noticed that scottie05 closed their account. Notifying arbitrator...
 

 
Date: Thursday Oct 13, 2011 3:10:04 PM (Arbitration Response Id: 1,684,156)
From: vWorker Agent (vWorker ) (Arbitrator)
To: scottie05 (employer),MOTASH  (worker),Tim Yates (vWorker)  (arbitrator)
 
Automated alert: vWorker.com noticed that scottie05 closed their account. Notifying arbitrator...
 

 
Date: Thursday Oct 13, 2011 3:10:04 PM (Arbitration Response Id: 1,684,157)
From: vWorker Agent (vWorker ) (Arbitrator)
To: scottie05 (employer),MOTASH  (worker),Tim Yates (vWorker)  (arbitrator)
 
Automated alert: vWorker.com noticed that scottie05 closed their account. Notifying arbitrator...
 

 
Date: Thursday Oct 13, 2011 3:10:04 PM (Arbitration Response Id: 1,684,158)
From: vWorker Agent (vWorker ) (Arbitrator)
To: scottie05 (employer),MOTASH  (worker),Tim Yates (vWorker)  (arbitrator)
 
Automated alert: vWorker.com noticed that scottie05 closed their account. Notifying arbitrator...
 

 
Date: Thursday Oct 13, 2011 3:30:08 PM (Arbitration Response Id: 1,684,164)
From: MOTASH (worker)
To: Tim Yates (vWorker)  (arbitrator)
CC: scottie05 (employer)
 
Tim,
the employer closed their account
Plz Advice
 

 
Date: Friday Oct 14, 2011 9:21:40 AM (Arbitration Response Id: 1,684,507)
From: MOTASH (worker)
To: Tim Yates (vWorker)  (arbitrator)
CC: scottie05 (employer)
 
Tim,

Sorry to post again,
but i'm really confused, and don't know what's the situation right now?
 

 
Date: Friday Oct 14, 2011 1:25:07 PM (Arbitration Response Id: 1,684,671)
From: Tim Yates (vWorker) (Arbitrator)
To: scottie05 (employer),MOTASH  (worker)
 
Motash,

Diane has closed their account and forfeited the arbitration.

After going through their comments and the arbitration, you were warned previously for giving opinions on Monday Sep 26, 2011 2:56:06 PM (Arbitration Response Id: 1,674,883). Because of this, you should have been forfeited the next time that you gave an opinion instead of a warning on Wednesday Oct 12, 2011 11:49:46 AM (Arbitration Response Id: 1,683,366).

You have also forfeited the arbitration for giving opinions after receiving a warning.

This arbitration will be closed shortly. The money will be refunded back to the employer.

Regards.
Tim Yates (vWorker)
 

 
Date: Friday Oct 14, 2011 2:06:15 PM (Arbitration Response Id: 1,684,704)
From: MOTASH (worker)
To: Tim Yates (vWorker)  (arbitrator)
CC: scottie05 (employer)
 
Tim,

First:
Regarding the first warning:
when you wrote"I believe that the employer is stating that there is a different issue on the 32 bit and I have asked for clarification."
Then this is a fact not opinion

while when i address that point,notify you that i expect allegation to be stated by employer not you, i wrote
"as a judging party,i expect you not to follow nor show what you THINK on behalf of any party, until BOTH parties show their allegations"
then i'm giving an opinion, wow !! that really needs explanation


Second:
you gave a circumstantial judgement when the employer tested on unagreed platform, you freed the employer of any liability twoards an admitted fault and said that my effort wasted to detect/report the employer fault is compensated by the escrow ,and time is uncounted since the project is in explicit state

what about now, you wrote "you should have been forfeited the next time that you gave an opinion",
so since i should have forfeited from 12-oct
1- who is responsible for that mistake
2- who pays now for my effort done since that date
3 who pays for my time spent since that date


Third:
Please be noted that the employer has closed his account on vworker, so if the escrow is returned to him,then if any further reopening/reviewing of this arbitration that goes in my favour, VWorker is responsible in front of me to pay me, hope that be clear and confirmed before any release of the escrow back to the employer
 

 
Date: Saturday Oct 15, 2011 12:43:17 AM (Arbitration Response Id: 1,684,868)
From: MOTASH (worker)
To: Tim Yates (vWorker)  (arbitrator)
CC: scottie05 (employer)
 
Besides:

Fourth:
as the project was already resumed,There's no single refrence in Worker contract to take my actions with a retroactive effect, except through 4b.13) Re-examining/re-opening arbitrations which requires the employer to be a party(he actually left)and is overruled by 3a1) 'Quick Resolution' Arbitrations "If either party closes their account, then they agree that they will forfeit any ongoing and/or future arbitrations"


Fifth:
if the employer is refuned 100% of escrow, my copyrights are protected by 4.6) When the Employer Wins Arbitration, which is not any more abiding the employer as he closed his account


Sixth:
even if both parties are found at fault, there's no single refrence that a forfeited employer is refunded(only winning employer do), on the other  hand i allege that the employer defaulted, prematurely quitted the project and arbitration by closing his account, and in such case clearly Vworker has to protect my time invested and i have to get compensated


Finaly but not the last,
Tim, as a representative of Vworker which acts as my agent which also provides its service in return for a fee paid by me,by 18. LIMITATION OF LIABILITY; INDEMNITY  i'm asking in case this arbitration went against me, what's my options to appeal the decisions made
 

 
Date: Monday Oct 17, 2011 1:33:28 PM (Arbitration Response Id: 1,685,707)
From: Tim Yates (vWorker) (Arbitrator)
To: scottie05 (employer),MOTASH  (worker)
 
Motash,

Final Warning:

You are not allowed to give opinions about any person, for any reason, even if you believe them to be true.

Statements such as the following are considered opinions:

you gave a circumstantial judgement...

If any more opinions are given, your account will be closed.

If you are having trouble understanding what is an opinion, I will be willing to explain the issue over the phone.


Please be noted that the employer has closed his account on vworker, so if the escrow is returned to him,then if any further reopening/reviewing of this arbitration that goes in my favour, VWorker is responsible in front of me to pay me, hope that be clear and confirmed before any release of the escrow back to the employer

You will be given an opportunity to appeal this decision. The escrow will not be released until you either decline the appeal or after the decision on the appeal.

what about now, you wrote "you should have been forfeited the next time that you gave an opinion",
so since i should have forfeited from 12-oct
1- who is responsible for that mistake
2- who pays now for my effort done since that date
3 who pays for my time spent since that date



as the project was already resumed,There's no single refrence in Worker contract to take my actions with a retroactive effect, except through 4b.13) Re-examining/re-opening arbitrations which requires the employer to be a party(he actually left)and is overruled by 3a1) 'Quick Resolution' Arbitrations "If either party closes their account, then they agree that they will forfeit any ongoing and/or future arbitrations"

If Employer or Worker threatens or harasses the other party or Exhedra, does not treat the arbitration process with respect or professionalism, does not follow arbitrator instructions, attempts (in Exhedra's sole opinion) to manipulate or unduly influence the arbitration process, or breaks any rules in the employer or worker agreement or in the site terms and conditions, then Exhedra may choose to automatically forfeit that party and rule in favor of the opposite party, as well as permanently terminate that party's account.


if the employer is refuned 100% of escrow, my copyrights are protected by 4.6) When the Employer Wins Arbitration, which is not any more abiding the employer as he closed his account

Since the employer has not paid for your work, then they would not be able to use your work. Should you discover that they are using your work, you may bring them to court.

even if both parties are found at fault, there's no single refrence that a forfeited employer is refunded(only winning employer do), on the other hand i allege that the employer defaulted, prematurely quitted the project and arbitration by closing his account, and in such case clearly Vworker has to protect my time invested and i have to get compensated

It is not stated anywhere in the Empoyer's Contract that this is the case.

Tim, as a representative of Vworker which acts as my agent which also provides its service in return for a fee paid by me,by 18. LIMITATION OF LIABILITY; INDEMNITY i'm asking in case this arbitration went against me, what's my options to appeal the decisions made

Mohamed,

You have the right to request a review of any decision made during arbitration. The arbitrators are human and since no human is perfect, a mistake can happen, even with the months of training that each arbitrator receives. When we find mistakes, we correct them. Our BBB and square trade record can attest to this, as we have never had an unresolved complaint.

However, on the other hand, when an arbitrator does their job 100% perfectly...it's guaranteed that 50% of people (the people who lost) will still not like the results. These people often want a review simply because they are unwilling to accept a proper judgment and are hoping that a 2nd person reviewing it will determine something differently. When this happens, it is not fair to the other party.

To prevent the review process from being abused, and simultaneously allow legitimate issues to be reviewed, the process works as follows:

1) If you tell me to, I will have this reviewed by a senior arbitrator (full instructions are below).
2) If they find that a mistake was made, then it would be corrected.
3) If they found no mistake was made, then nothing would change. Further, if it was determined that you initiated this review without a sufficiently good reason, then the attempt to unfairly delay the arbitration would result in your loss of the arbitration and permanent closing of your account.

If you would like the review, then there is one other thing to understand. A review can only occur on decisions that have been already made in this arbitration. If a final decision was not made on an issue, then obviously it can't be reviewed. If this is your situation, you can choose to wait until the issue is ruled on, before choosing to request a review.

The decisions made in this arbitration are:

1. The worker was forfeited for posting opinions and behaving unprofessionally.


Mohamed,

A) Please respond and say either "I want an arbitration review" or "I decline the arbitration review".
B) If you choose the review, please also tell me:
B1) The #(s) of the decision(s) you want reviewed.
 Do not send details at this point...that will happen later during the review.
B2) Confirm that you understand and agree to the rules for a senior arbitrator by reposting this entire quote to me:

"I understand and agree that the arbitrator will only review the decision(s) above. If they find the decision was incorrect, then it will be changed. If they find it was correct, then it will not be changed. Further, if it was correct, and the arbitrator cannot find a legitimate reason for me to have requested this review, then I understand and agree that I will forfeit the arbitration and my account permanently."

Mohamed, please respond to the bold items above and then we can continue. Thanks.



Regards.
Tim Yates (vWorker)

P.S. Automated warning about upcoming deadline(s). Worker must respond before Thursday Oct 20, 2011 1:33:28 PM EDT. If you can respond sooner, please do so, as it will speed up the arbitration process for both parties. Thanks.
 

 
Date: Tuesday Oct 18, 2011 3:06:23 AM (Arbitration Response Id: 1,685,999)
From: MOTASH (worker)
To: Tim Yates (vWorker)  (arbitrator)
CC: scottie05 (employer)
 
Tim,

First of all : i don't ask the escrow either be refunded to employer nor released to me nor delayed by any means, escrow decision is a sole action of Exhedra , and at any time Exhedra alone will be responsible for her decisions

- for the record, i don't agree with your given answers in your last arbit. response

- while for "opionion", yes please give me more details to better understand your point, your phonecall is welcome, but i believe if you give me (a list of opinions i gave during arbit. and why they are considered so) would be better, and plz send it as email, as it will not be a subject of argument from my side, nor does affect the progress of arbitration

Finally regarding "arbit. review" :

I don't see any refrence for the terms of this process in my contract(correct me if i'm wrong), which means :
1- for me it's an action of "free will"
2- my "free will" decision does not affect the decisions already made for this arbitration
so, giving me such choice(again, it's not in the contract) will not be subject to arbitration terms, that i must answer and within 3 days
so shall you take your decisions regarding this arbitration, and i have my choices open, and afterall even we all are humans, but held responsible for our decisions
 

 
Date: Tuesday Oct 18, 2011 3:10:37 AM (Arbitration Response Id: 1,686,000)
From: MOTASH (worker)
To: Tim Yates (vWorker)  (arbitrator)
CC: scottie05 (employer)
 
Tim,

you know, your phone call regarding opinions will be much appreciated
 

 
Date: Tuesday Oct 18, 2011 3:58:48 PM (Arbitration Response Id: 1,686,616)
From: Tim Yates (vWorker) (Arbitrator)
To: scottie05 (employer),MOTASH  (worker)
 
Motash,

For the phone call, I am available from 8 to 4 EST (GMT - 5). Do you have skype? We can go through the opinions in the arbitration on the phone.

You wrote:

I don't see any refrence for the terms of this process in my contract(correct me if i'm wrong), which means :
1- for me it's an action of "free will"
2- my "free will" decision does not affect the decisions already made for this arbitration
so, giving me such choice(again, it's not in the contract) will not be subject to arbitration terms, that i must answer and within 3 days
so shall you take your decisions regarding this arbitration, and i have my choices open, and afterall even we all are humans, but held responsible for our decisions


The contract says:

Exhedra's goal in arbitrations is to always arrive at a fair arbitration result. Sometimes such a result is difficult to attain, for example, due to lack of complete information, miscommunication, etc.. If Exhedra determines (at its sole discretion) that an arbitration result was not (or may not) have been 100% correct, it has the right to re-examine and/or re-open any and/or all parts of it. If Exhedra (at its sole discretion) determines that a change should be made, the new change takes precedence over any original resolution. If Exhedra re-opens an arbitration, all parties have the same rights, duties and responsibilities as in a normal arbitration.

The contract does not state that you are required to receive an arbitration review. The instructions in Arbitration Response Id: 1,685,707 are what we use for arbitration reviews. If you want a review, those are the rules you must follow. I have not extended the deadline for your response.

Regards.
Tim Yates (vWorker)
 

 
Date: Tuesday Oct 18, 2011 4:43:43 PM (Arbitration Response Id: 1,686,629)
From: MOTASH (worker)
To: Tim Yates (vWorker)  (arbitrator)
CC: scottie05 (employer)
 
Tim,

my skype is :  motash
if you still have time today, i'd be happy to get in contact, else we can arrange that tomorrow
sorry if i'm suggesting near dates, but i hope that you understand that, discussing that point ( opinions) will make me more acceptable/understanding to decisions made, if (to me)logic justifying decisions was found

while for Arbitration Review :

My clear answer :
- since the review terms were not previously agreed between me and exhedra (not mentioned in the worker contract), then
1- i can't be forced to accept/refuse it under any conditions ( an arbitrator question, limited by 3days period)
2- any time discussing/accepting/refusing these review terms(not previously agreed) doesn't affect what is already agreed, that arbitrations partially/fully can be reviewed/reopened


 

 
Date: Wednesday Oct 19, 2011 12:34:56 PM (Arbitration Response Id: 1,686,972)
From: MOTASH (worker)
To: Tim Yates (vWorker)  (arbitrator)
CC: scottie05 (employer)
 
May i pose a generic question:
- since i started this arbitration to settle disputed contract terms, and the arbitration reached a result about the terms, and the final target was attained ( determining what work is left, and put a deadline), and both parties abide by decison and project resumed on 11-october

what's the reason behind the arbitration is still open after 11-oct till now, any questions/discussions from my side can be done through support, my contract grants me the support/advice/response from any Exhedra individual?
besides the scenario would be different, as all my questions are expected to be answered,and i'll not be bound to repsond within time limits(on the contrary, the representant of exhedra should)
 

 
Date: Wednesday Oct 19, 2011 12:38:41 PM (Arbitration Response Id: 1,686,974)
From: MOTASH (worker)
To: Tim Yates (vWorker)  (arbitrator)
CC: scottie05 (employer)
 
also, what's your skype id, or how should a contact happen?
 

 
Date: Wednesday Oct 19, 2011 3:28:35 PM (Arbitration Response Id: 1,687,193)
From: Tim Yates (vWorker) (Arbitrator)
To: scottie05 (employer),MOTASH  (worker)
 
Motash,

You wrote:

My clear answer :
- since the review terms were not previously agreed between me and exhedra (not mentioned in the worker contract), then
1- i can't be forced to accept/refuse it under any conditions ( an arbitrator question, limited by 3days period)
2- any time discussing/accepting/refusing these review terms(not previously agreed) doesn't affect what is already agreed, that arbitrations partially/fully can be reviewed/reopened


The review terms are not negotiable and your response deadline has not been extended.

what's the reason behind the arbitration is still open after 11-oct till now, any questions/discussions from my side can be done through support, my contract grants me the support/advice/response from any Exhedra individual?
besides the scenario would be different, as all my questions are expected to be answered,and i'll not be bound to repsond within time limits(on the contrary, the representant of exhedra should)


The arbitration is still open because you have not responded to the question of whether you are going to request a review or not. If a review is requested, the arbitration will stay open, otherwise it will be closed at that time.


In regards to the phone call, are you available for me to call you at 9:30 EST tomorrow?

The phone call is strictly to ensure that you understand what an opinion is. If you are unable to understand the issue regarding giving opinions, then you can no longer continue working on the vworker site.



Regards.
Tim Yates (vWorker)
 

 
Date: Wednesday Oct 19, 2011 3:58:00 PM (Arbitration Response Id: 1,687,213)
From: MOTASH (worker)
To: Tim Yates (vWorker)  (arbitrator)
CC: scottie05 (employer)
 
Tim,

My answer is always the same:
The part of the contract you mentioned on Arbitration Response Id: 1,686,616 , does not mention any of these review terms, so These review terms are not part of the contract i agreed to, along with Exhedra, correct me if i'm wrong?

while for, why is arbitration open:
your question started 17-oct, in my question, did you notice the "11-oct" date?

finally regarding the phone call:
- i gave you my skype id, just give me yours, and i'll call you tomorrow during your working hours
- you wrote "The phone call is strictly to ensure that you understand what an opinion is. If you are unable to understand the issue regarding giving opinions, then you can no longer continue working on the vworker site."
my reply:just let the contract determine that
 

 
Date: Wednesday Oct 19, 2011 4:17:31 PM (Arbitration Response Id: 1,687,226)
From: Tim Yates (vWorker) (Arbitrator)
To: scottie05 (employer),MOTASH  (worker)
 
Motash,

The part of the contract you mentioned on Arbitration Response Id: 1,686,616 , does not mention any of these review terms, so These review terms are not part of the contract i agreed to, along with Exhedra, correct me if i'm wrong?

If you went by the contract, you would not receive a review at all.

while for, why is arbitration open:
your question started 17-oct, in my question, did you notice the "11-oct" date?


The project was still in arbitration at this time. The project did not leave arbitration on October 11.

finally regarding the phone call:
- i gave you my skype id, just give me yours, and i'll call you tomorrow during your working hours
- you wrote "
The phone call is strictly to ensure that you understand what an opinion is. If you are unable to understand the issue regarding giving opinions, then you can no longer continue working on the vworker site.
"
my reply:just let the contract determine that


You will need to select a time for the phone call. If 9:30 EST is not available, please select a new one.

 you wrote "The phone call is strictly to ensure that you understand what an opinion is. If you are unable to understand the issue regarding giving opinions, then you can no longer continue working on the vworker site."
my reply:just let the contract determine that


Please confirm that you understand that this phone call is only about offering opinions. If you do not, then there will not be a phone call.

Regards.
Tim Yates (vWorker)
 

 
Date: Wednesday Oct 19, 2011 5:17:43 PM (Arbitration Response Id: 1,687,272)
From: MOTASH (worker)
To: Tim Yates (vWorker)  (arbitrator)
CC: scottie05 (employer)
 
Tim,

you wrote "If you went by the contract, you would not receive a review at all"
and also wrote "You have the right to request a review of any decision made during arbitration"
these replies makes me confused

you wrote "The project was still in arbitration at this time. The project did not leave arbitration on October 11"
and this takes me back to the original generic question:
if the target of this arbitration was attained and the project was resumed on 11-oct, why is the project in arbitration after 11-oct ?


i have to repeate what i wrote on Arbitration Response Id: 1,685,999
"i don't ask the escrow either be refunded to employer nor released to me nor delayed by any means, escrow decision is a sole action of Exhedra , and at any time Exhedra alone will be responsible for her decisions"


I confirm that the phonecall is about opinions only , and i never said other than that
i wrote "just let the contract determine that "
in reply to what you wrote "If you are unable to understand the issue regarding giving opinions, then you can no longer continue working on the vworker site."

while for availability,is 9:30 - 10:00 AM EST (15:30 - 16:00 PM my time)ok with you?
 

 
Date: Thursday Oct 20, 2011 9:30:00 AM (Arbitration Response Id: 1,687,476)
From: Tim Yates (vWorker) (Arbitrator)
To: scottie05 (employer),MOTASH  (worker)
 
Motash,

you wrote "If you went by the contract, you would not receive a review at all"
and also wrote "
<font color="#000000" size="2">You have the right to request a review of any decision made during arbitration"
</font>
these replies makes me confused

You have a right to request a review of the decision, however, that review is not guaranteed.


you wrote "
The project was still in arbitration at this time. The project did not leave arbitration on October 11"
and this takes me back to the original generic question:
if the target of this arbitration was attained and the project was resumed on 11-oct, why is the project in arbitration after 11-oct ?



I believe that you are asking why the project was still in arbitration after the decision was made, the reason is that the project was still in arbitration and work was continuing. There was no discussion to bring the project out of arbitration. Work can continue in arbitration.

i have to repeate what i wrote on Arbitration Response Id: 1,685,999
"i don't ask the escrow either be refunded to employer nor released to me nor delayed by any means, escrow decision is a sole action of Exhedra , and at any time Exhedra alone will be responsible for her decisions"


I am not sure what you are stating here.

I confirm that the phonecall is about opinions only , and i never said other than that
i wrote "
<font color="#808000" size="2">just let the contract determine that
</font> "
in reply to what you wrote "
If you are unable to understand the issue regarding giving opinions, then you can no longer continue working on the vworker site."



Thank you.

while for availability,is 9:30 - 10:00 AM EST (15:30 - 16:00 PM my time)ok with you?

This is acceptable, I will contact you shortly. My skype id is tim.yates314


Regards.
Tim Yates (vWorker)
 

 
Date: Thursday Oct 20, 2011 10:40:58 AM (Arbitration Response Id: 1,687,533)
From: Tim Yates (vWorker) (Arbitrator)
To: scottie05 (employer),MOTASH  (worker)
 
Motash,

Thank you for taking the phone call.

Summary of the conversation:

We discussed various scenarios regarding what is an opinion and what is not an opinion. I stated that you are not allowed to give an opinion about another person even if you believe them to be true.

Motash listed several statements by the employer and we discussed if they were opinions or not.

Motash,

Please confirm the summary. If I have missed anything, please let me know. One item I did not mention is that if you believe the other party is giving opinions and the arbitrator is not addressing it, you may bring it to their attention.

As a reminder, the deadline for responding for an arbitration review is Thursday Oct 20, 2011 1:33:28 PM.


Regards.
Tim Yates (vWorker)

P.S. Automated warning about upcoming deadline(s). Worker must respond before Tuesday Oct 25, 2011 10:40:58 AM EDT. If you can respond sooner, please do so, as it will speed up the arbitration process for both parties. Thanks.
 

 
Date: Thursday Oct 20, 2011 10:59:45 AM (Arbitration Response Id: 1,687,546)
From: MOTASH (worker)
To: Tim Yates (vWorker)  (arbitrator)
CC: scottie05 (employer)
 
Tim,

I have a right(neither written in the contract, nor the review terms), and even if it's my right, the action is not gurranteed
The whole review thing is ambigous, and this arbitration has taken alot of my time and effort
If it's my right(undocumented) to request a review, i'd like to keep that right(without accepting any terms at the moment), till i review my options ( giveup , go in public,get a review,file a lawsuit,...)

finally, didn't you get curious to check if my code is working as per the contract or not?
or the option to check for a completion percentage to protect my invested time , against an employer who is in default(Employer Contract 17. DEFAULT;TERMINATION) of testing/accepting my work(by closing his account), were never available ?
 

 
Date: Thursday Oct 20, 2011 12:42:25 PM (Arbitration Response Id: 1,687,634)
From: MOTASH (worker)
To: Tim Yates (vWorker)  (arbitrator)
CC: scottie05 (employer)
 
Tim,

thanks for the call , i confirm the summary

on the other hand, yes i believe that the employer did have statments, that need to be put under arbitrator attention to decide if they are opinions or not, and it's of a high importance, as if found opinions,may lead to different decisions

A list of employer statments :

1- Tuesday Sep 6, 2011 5:36:39 PM (Arbitration Response Id: 1,663,968) :
- "The developer is asserting that, because it works in his development environment, that is good enough."

2- Friday Sep 9, 2011 1:59:31 PM (Arbitration Response Id: 1,665,805):
- "I thought I had a good working relationship with this developer, but I no longer think so."

3- Tuesday Sep 27, 2011 1:24:52 PM (Arbitration Response Id: 1,675,414) :
-"No indication that the arbitration is complete has been made anywhere in the project thread, although I have to assume that, at this point, it is, according to Arbitration Response Id: 1,674,916. that rules in my favor."
- "i've received no answer to my subsequent question, so I have assumed arbitration is complete and I am re-commencing working with the worker."

4- Friday Sep 30, 2011 4:47:24 PM (Arbitration Response Id: 1,677,320) :
- "It does not seem possible to get a single, straightforward answer from this developer that I can understand."

5- Friday Oct 7, 2011 11:55:51 AM (Arbitration Response Id: 1,681,005) :
- "We did not initiate this unwarranted arbitration"

6- Wednesday Oct 12, 2011 3:07:29 PM (Arbitration Response Id: 1,683,555)
- "So that the developer does not have grounds for any more libellous accusations, nor the arbitrator further suggest we might somehow be stalling/retaliating, we are documenting these fully"
- "We do not believe this developer is competent to complete the work as specified."

7- Wednesday Oct 12, 2011 3:28:37 PM (Arbitration Response Id: 1,683,565) :
- "Am I no longer protected, simply because the worker decided to arbitrate instead of addressing the defect list I reported at that time?"

8- Thursday Oct 13, 2011 11:55:01 AM (Arbitration Response Id: 1,683,960)
"Such an accusation is another falsehood, and I suspect the arbitrator will continue to ignore violations to the arbitration agreement."

9- Thursday Oct 13, 2011 3:00:28 PM (Arbitration Response Id: 1,684,134)
-"Because vworker has not followed its own arbitration rules (so called opinions above are not opinions, and meet the legal definition of libel) and has unnecessarily delayed arbitration"
-"This arbitration has not been remotely fair or impartial whatever you and your policies claim. You have repeatedly ignored transgressions by the worker and forced my actions based on one technicality while ignoring others at your convenience."
-"If you wish to release those funds to this incompetent, untruthful, insulting, and combative worker, and refuse to warn others what could happen to them if they pick him"
-"but I will not add insult to injury by testing his horribly unstable and inadequate code in my test lab any longer."


Thanks,
MOTASH


 

 
Date: Thursday Oct 20, 2011 12:48:39 PM (Arbitration Response Id: 1,687,645)
From: Tim Yates (vWorker) (Arbitrator)
To: scottie05 (employer),MOTASH  (worker)
 
Motash,

Thank you for confirming the summary.

You wrote:

on the other hand, yes i believe that the employer did have statments, that need to be put under arbitrator attention to decide if they are opinions or not, and it's of a high importance, as if found opinions,may lead to different decisions

If you want to bring this up in an arbitration review, that is fine. You have approximately an hour to confirm that you wish to go for a review as the deadline expires soon.

Regards.
Tim Yates (vWorker)
 

 
Date: Thursday Oct 20, 2011 2:06:22 PM (Arbitration Response Id: 1,687,750)
From: MOTASH (worker)
To: Tim Yates (vWorker)  (arbitrator)
CC: scottie05 (employer)
 
Tim,

this whole arbitration was started because of one term(one of other tons) in my contract with employer, so far i have learned never to get into something i'm not fully aware of its limits, and the rules governing it

so far, what i know about arbit. review (may be later you correct me if i'm wrong):-
- not gurranteed
- it has extreme limits (reaching account closed for me, while on the other side considers the arbitrator if went wrong as a human act)
- limited range of argument ( only the final decision which is more like a verdict, with no reasoning and supporting refrences)
- having internal Exhedra governing rules(which for the first glance, seems that can be changed anytime with any notice)

so i prefere to keep my options open, while i'd do my best to reach a fair result for this arbitration
 

 
Date: Thursday Oct 20, 2011 2:56:05 PM (Arbitration Response Id: 1,687,814)
From: MOTASH (worker)
To: Tim Yates (vWorker)  (arbitrator)
CC: scottie05 (employer)
 
Tim,

correction: i understand that english is the formal language in this arbitration, and i apologize on arbit. respose id 1,687,546 for saying "is in default of", while i meant "he dropped behind testing/accepting ... (employer contract 17...) "
 

 
Date: Friday Oct 21, 2011 9:47:24 AM (Arbitration Response Id: 1,688,189)
From: Tim Yates (vWorker) (Arbitrator)
To: MOTASH  (worker)
CC: scottie05 (employer)
 
Note: 1 long word(s)/URL(s) in this posting > 65 characters was/were broken up with spaces to prevent it/them from stretching the screen and making it difficult to read.

Scottie05 (the employer) forfeited arbitration because they closed their account. MOTASH (the Worker) forfeited arbitration because they continued to give opinions about the other party after being warned not to. Both parties were given a poor rating. All funds in escrow were refunded to scottie05.

Arbitration has been closed, in accordance with the rules and regulations of the site.


Sincerely,
Tim Yates (vWorker)
vWorker.com Arbitrator
============================================
www.vWork er.com
Need an expert? Hire the best and brightest global talent
with the safety of a money back guarantee!

P: (813) 908-9029
F: (813) 960-1495
E: TimYates@exhedra.com
Exhedra Solutions, Inc.
============================================
 

 
Date: Friday Oct 21, 2011 9:47:25 AM (Arbitration Response Id: 1,688,190)
From: Tim Yates (vWorker) (Arbitrator)
To: scottie05 (employer)
 
 This message was sent privately

Note: 1 long word(s)/URL(s) in this posting > 65 characters was/were broken up with spaces to prevent it/them from stretching the screen and making it difficult to read.

     The project has been closed and the funds released from escrow and awarded back to your vWorker.com account. As always, your current balance and transaction history can be viewed from 'My financials' under 'My account' in the menu.

     Here are your choices at this point:

     1) You can choose a new worker by either:

     1a) ...perusing the older bidders on your project. You can refresh your memory on the bids you received by going to project control panel and clicking on 'Messages summary'. If you'd like to talk further to one, you can do this by reactivating the project (again from your project control panel), and then corresponding in the same way that you did with this bidder. You can also accept their bid in the same way. If you do this, the site will automatically apply the funds in your account toward the new bid amount.

     1b) ...starting from scratch with fresh bidders. This is a good option if you want to get some new people bidding on your project. If you find one that you like, the site will automatically apply the funds in your account toward the new bidder. To repost, go to your project control panel and click on "Repost this project". (Please note that since you selected a worker, reposting will NOT adversely effect your non-action ratio.)

     Or

     2) You can have your funds:

     2a) ...Left in your vWorker.com account for use on future projects. In the future, if you select someone, the site will automatically apply the funds in your account toward your new bidder. If you want this option, you don't have to do anything...the funds are already credited to your account.

     2b) ...Refunded to your credit card or Pay Pal account. Please be reminded that we incur a financial charge in doing this, which is why we charge a 3.5% refund charge to cover this, as was disclosed in your employer contract and the employer FAQ. However...if you negotiated for an Expert Guarantee on this project, and the worker forfeited it, then it will be used to cover this charge instead. OR...if the worker was found at fault (and has funds in their account to cover it) they will assume this charge (per their contract) rather than you. If you want a refund, please inform finance of the amount you want refunded and they will arrange it.

     Since this arbitration is now closed, you won't be able to reply back on the arbitration itself...but if you still have questions, you can email me directly at: TimYates@exhedra.com.


Sincerely,
Tim Yates (vWorker)
vWorker.com Arbitrator
============================================
www.vWork er.com
Need an expert? Hire the best and brightest global talent
with the safety of a money back guarantee!

P: (813) 908-9029
F: (813) 960-1495
E: TimYates@exhedra.com
Exhedra Solutions, Inc.
============================================
 

 
Date: Tuesday Jan 24, 2012 11:57:51 AM (Arbitration Response Id: 1,732,650)
From: Rafeek Kulkarni (vWorker) (Arbitrator)
To: Tim Yates (vWorker)  (arbitrator)
 
Attached File
0.01 MB

 This message was sent privately

This is a Dummy upload.

Rafeek Kulkarni (vWorker)
 

 
 
  Current end of arbitration for Winsock monitor command line tool: (Messages | Project)